Summary of NCSX SIT Meeting of Monday, Apr. 21, 2003
1. PDR Preparation Schedule
Preparations for the PDR are behind schedule. Progress in
some areas is slower than expected, and consequently there is risk that we may
not be ready for the PDR on June 24, the current schedule. A 2-3-month
delay in the PDR (from June to Aug. or Sept.) may be the prudent course to
greatly improve the chances of being successful. The issues bearing on a
possible delay were discussed.
* Modular coil geometry modeling. -Brad
The M50_256.z01 coil pack orientation is being manually
optimized (by Dave W.) to create enough space between coils for structure,
clamps, etc. in the tight spots on the inboard side. This is a time-consuming
manual process, but it is progressing. Brad's expectation is that Z01 will
ultimately work but it is difficult to predict how long it will take.
Meanwhile, details are being added to the model, such as the poloidal break,
clamps, cooling, and outer shell surface details.
* Possibilities for improving the coil geometry. -All
Some of the coil pack build elements have grown,
exacerbating the crowding problem and pushing up current density. If we could
reduce the build in the tight spots, it could help the geometry optimization.
Elements to look at:
- Insulation thickness
- Tee thickness
- Copper packing fraction
- Clamps
- Cooling tubes, copper strips.
- Potting mold.
We will review these at the next WBS 1 meeting, this
Wednesday 4/23. ACTION: Brad.
Various winding-law modifications have been tried recently
but so far all failed the PIES test. The perturbation from Z01 to E01 caused a
significant loss of magnetic surfaces, but the perturbation from E01 to E03 did
not make it worse. Thus, manual winding-law perturbations are not out of the
question. They would have to be checked for physics properties and magnetic
surfaces.
* Winding pack properties and allowables. -Brad
We are depending on test data from CTD and UT to define
properties and allowables needed for structural and thermal analysis. The
testing is late getting started. As a workaround, the plan is to proceed with
the analysis using upper and lower bounding values. This will support the June
24 PDR schedule if the test results are within the assumed bounds. The risk is
that they will be out of bounds with no time left to modify the design to
react.
* MCWF and VV budgetary cost estimates from the
suppliers. -Phil
The MCWF contracts were placed a few weeks ago and the
suppliers are working on their Phase I tasks. They are using the proposal
drawings (CDR design with modifications such as the poloidal break). They are
working to a May 23 deadline for budgetary estimates, with formal reports to
follow about 2 weeks later. This supports the June 24 schedule. The risk is that
it leaves little time to iterate if the estimates are high.
The VV contracts were just awarded and kickoff meetings are
being scheduled. We will ask them to support the May 23 deadline for budgetary
estimates.
MCWF and VV Prototypes: Not needed for the PDR but important
for the FDR. We will soon need to authorize the suppliers to start on prototype
fabrication tasks. We need to decide in about two weeks what drawings we want
them to use.
ACTION: Brad.
* Re-baselining. -Ron
Updated estimates are coming in from WBS managers, but some
are expected to be late. Nominally supports the June 24 schedule but leaves
little time for iteration if needed to control cost and schedule growth.
ACTION: Ron to develop a schedule for collecting, reviewing,
and compiling the updated estimates.
* Implications for downstream schedule and budgets. -Ron
The design delays imply a 3-month delay in the modular coil
FDR, and a 2-month delay in the VV FDR. A 3-month delay in the PDR is
consistent with that. Procurement of the MCWF and VV would be correspondingly
delayed. However, TF and PF procurements, previously delayed to FY05 because of
budget constraints, could be accelerated to FY04. The delay in the critical
path could be made up in the field-period assembly phase by going to double
shift, preserving the first plasma date the schedule contingency.
It was pointed out that work packages not affected by the
modular coil design problems could proceed as planned or even accelerate. By
September, the TF and PF could be ready for their PDRs. If the Project PDR were
held then, the TF/PF PDRs could be folded in, making it a more complete review.
This is a silver lining if we decide to delay.
* Swapping the order of the QPS CDR and NCSX PDR. -Jim
If the NCSX PDR is delayed, the QPS CDR will be moved up to
June. Preparations will have to start immediately. Part of the ORNL
design effort will shift attention to QPS to support the CDR preparations.
Critical tasks supporting the NCSX PDR would be affected but would not be
interrupted. With careful planning and some load re-balancing between PPPL and
ORNL, we should be able to manage this.
Further discussions with Lab management and DOE are planned
this week before making a decision. The consensus recommendation of the
SIT is to delay the PDR at least to August.
2. Next SIT Meeting: Monday, April 28, 2003.
Summary by:
Hutch Neilson