Summary of NCSX SIT Meeting of Monday, August 11, 2003

 

1. Project Scope and Cost for the PDR

A discussion was held on the project's objectives in developing the PDR baseline.

 

The project's goal is to baseline the project with a cost objective of $73.5M (same as the current baseline), including 28% budget contingency on the remaining work as of 10/1/03. To accomplish this, further scope reductions are necessary.

 

The WBS 5 cost review meeting on August 8 resulted in decisions to significantly streamline the Day-1 Central I&C and Data Acquistion System, with substantial cost savings expected. An updated estimate will be submitted by G. Oliaro in about 2 weeks.

 

Reiersen recommended a simplified Day-1 power supply configurations which minimizes the number of circuits (6), power supply sections (6), and cables (12). The same power supply configuration (with some coil reconnections) is satisfactory for both first plasma and initial field line mapping at B=0.5 T and room temperature coils. The recommended configuration was approved and these requirement will be given to Ramakrishnan for use in developing the WBS 4 design and estimates.

 

Reiersen recommended leaving the cryostat partially uninstalled through first plasma and an initial period of field line mapping and engineering testing. This will facilitate access to the device for making adjustments to coils or leads should it be necessary to correct field errors during field mapping. Cryostat installation would have to be completed before diagnostics and other peripherals start getting installed, otherwise it would probably be too difficult to fit it in. The consensus was that the cryostat design and fabrication costs, and some of the installation costs, should be kept in the MIE project estimate, but some of the installation costs could be deferred.

 

There was a discussion about how much useful work could be done with room temperature coils. The performance limits were reported to be 0.5T for 3 s (coil-heating-limited) for initial field line mapping, and 0.75T for short pulse (power-supply-voltage-limited) for plasma operation but without NBI since the orbit losses would be too high. Thus we could start with RT operation but would probably want to complete the cryostat installation and move to cryogenic operation within 6 months or less.

 

The availability of nontrivial room-temperature performance means that we can consider deleting the cryogenic and VV bakeout systems from the MIE scope and complete them on operating funds. Issues are:

* How long would it take to implement these systems?

* What temporary provisions (e.g. water cooling of the coils) would be needed to support room temperature operation and what would they cost?

ACTION: Larry Dudek to follow up on these.

 

Zarnstorff emphasized the importance of having NBI available for obtaining compelling physics results as early in the program as possible. Work needs to start on it well before first plasma. If it were deleted from the MIE scope there is a risk of significant delay in NBI, since it is not known to what extent hardware fabrication activities will be supported under research preparation while the MIE project is in progress.

 

The present program plan has field mapping as the first research activity after first plasma. If the field mapping apparatus were deleted from the MIE scope there is a risk of significant delay in starting the research program.

 

Strategy for scope cutting from the MIE project:

 

* The power supply and I&C systems descopings being discussed can be done without impacting the "nameplate" performance ratings of the machine and we should go as far as we can with those.

* Leaving the cryostat uninstalled for a few months is technically advantageous and we should plan on it. At most, it only saves part of the installation costs but every bit helps.

 

After that, the impacts become more visible and the programmatic risks rise significantly:

 

* Next to go would be the cryogenic and VV bakeout systems provided the temporary systems to support RT operation don't chew up all the savings.

* Next to go would be NBI.

* Last to go would be field mapping apparatus.

 

2. PDR Preparations

 

* Panel

Ten people have agreed to serve on the PDR committee:

Jim Anderson (retired from LANL), Paul Anderson (GA), David Anderson (U.Wisc), Dan Driemeyer (Boeing), Jim Irby (MIT), Ray Johnson (ORNL/SNS), Steve Knowlton (Auburn), Jörg Sapper (retired from IPP), Carl Strawbridge (ORNL/SNS), and Peter Wanderer (Brookhaven).  Chair will be Strawbridge. Deputy chairs will be D.Anderson (magnets) and Driemeyer (vacuum vessel). The committee makeup will be reviewed for coverage of all areas and additional members will be recruited if necessary. Per DOE wishes, the panel has a strong non-fusion representation and management issues have been added to the scope of the review.

 

* Preliminary Design Report Preparations

Documentation guidance has been issued to authors and preparation schedules are incorporated in the WAFs. A summary plan and schedule for report preparation is needed to facilitate tracking.

ACTION: Wayne.

 

3. MCWF Schedule

The modular coil winding forms have fallen behind schedule by about 2 months relative to the July 1 baseline because of design delays. Release for prototype fabrication is now forecast for October 14, jeopardizing critical downstream milestones such as the FDR and release for production.

ACTION: Brad identify workarounds to improve the schedule.

 

4. Next SIT Meeting: Monday, August 18, 2003.

 

 

Summary by:

Hutch Neilson