1.
Vacuum Vessel Design and Interface Issues
ACTION:
Dick Majeski provided updated ICRF requirements to Mike Cole.
ACTION: Dave Johnson, Brent Stratton, finalize WBS 3 requirements.
Possible
solutions:
-
Modify
plasma shape or aspect ratio magnetically to increase clearance at the
tight spots.
-
Reduce
PFC space envelope in tight spots (easy if 350C VV bakeout is
adopted).
-
Small
model corrections (“tweaking”) to resolve local problems. (A.
Brooks)
-
Re-segmentation
to 6 segments (3x2/3-period, 3x1/3-period). A. Brooks will
discuss on 12/3.
-
Re-segmentation
to 9? segments with joints made up in field-period assembly and final
assembly.
Physics
issues will be discussed at meeting on December 2 at 1:30 p.m.
Re-segmentation ideas will be discussed at WBS 1 meeting on December 3 at
1:30 p.m.
Cost and schedule impact of the re-design effort to modify the
segmentation needs to be estimated if it is proposed. (ACTION: Brad)
2. Modular Coil Modeling and Analysis Issues
A
meeting will be held later this week to assess the Hargrove, Brown, and
Williamson modeling approaches, and decide on the path forward for the
project. The analysts (i.e. H.M.Fan) will be included in the discussions
and their needs will be taken into account to ensure we are able to
analyze what is designed.
ACTION: Brad, follow up.
3. CD-2 Preparation Plan
Most
of the required documentation is already in good shape. Outstanding tasks:
-
Project
Execution Plan: All signatories should be reviewing content other than
cost and schedule, which is highlighted in yellow and subject to
change after review recommendations are assessed. Comments to Bob
Simmons.
-
EIR
disposition plan: Assignees have been identified by Schmidt,
Strykowsky, and Neilson. Assignments will be issued Dec. 2. Replies
will be due to Bob Simmons.
-
PBR
disposition plan: Wayne and Hutch will identify assignees. Assignments
will be issued Dec. 2. Replies will be due to Bob Simmons.
-
Resource-loaded
schedule incorporating baseline changes. Ron is responsible.
-
CD-2
approval document. OFES is responsible.
Proposed schedule agreed to with DOE:
-
Finalize
disposition plans by Dec. 12.
-
Finalize
changes to the cost & schedule baseline (including contingencies)
by Dec. 19.
-
Updated
resource-loaded schedule and ECP by Jan. 9.
-
CD-2
ESAAB, week of Jan. 26.
4. Next Lehman review
We
favor early May, 2004, which precedes the VV and MC final design reviews.
The plan is to use the Lehman review to obtain necessary approvals
for CD-3a.
ACTION: Hutch convey SIT recommendation to DOE, and understand timing
issues with respect to FDR’s and CD-3 deliverables.
5. Next SIT Meeting: Monday, December 8, 2003 (GHN to
participate from ORNL)
Summary by:
Hutch Neilson
|