From: Hutch Neilson [hneilson@pppl.gov]
Sent: Tuesday, 
December 09, 2003 9:27 AM
To: Mike Zarnstorff; Wayne Reiersen; Bob 
Simmons; Larry Dudek; Ron Strykowsky; Brad Nelson; John Schmidt; Hutch Neilson; 
Jim Lyon
Subject: Summary of NCSX SIT Meeting of 12/8/03
Summary of NCSX System Integration Team (SIT) Meeting of Monday, 
December 8, 2003
1.  Vacuum Vessel Schedule Risks
We 
are making progress in coming to closure on the critical vacuum vessel design 
decisions:
  - We will likely retain the current vacuum vessel 
  segmentation scheme. The alternatives have too many unknowns for this stage of 
  the design, consequently high risk to the design schedule. We expect to 
  confirm this decision at next SIT. 
  
 - This week, Art Brooks will tweak the vacuum vessel 
  shell geometry to try to increase plasma-wall spacing within the existing 
  segmentation and assembly constraints. 
  
 - On 350 C bake, we will try to wrap up the decision by 
  next SIT, but the way things appear to be heading is:
  
    - The tube attachment issue can be resolved by 
    eliminating the requirement to cool the vessel. If they only have to heat 
    the vessel (a slow process), mechanical attachments (clips) can be used, 
    avoiding the need for high-temperature epoxy or welding. Electrical heaters 
    need to be installed on the ports. The program risk is that the cooldown 
    time for 12 MW plasma pulses my be longer than 15 mins. The benefits are 
    increased plasma-wall space and reduced operational costs and risk due to 
    thinner PFCs that do not need a separate cooling loop, except possibly for 
    local hot spots such as divertor plates. 
    
 - The thermal expansion issue is probably limited to 
    port interferences requiring some modifications of the port ducts, but 
    currently thought to be workable. The homework still needs to be finished on 
    this issue. ACTION: Goranson. 
    
 - The thermal cycling of the vacuum vessel at ~400 C is 
    thought not to be a feasibility issue but could be prohibitively costly. 
    ACTION: Goranson to follow up with suppliers.
 
The goal is to resolve the 350C bakeout issues this week and 
  decide at the next SIT.
 
  - In a separate discussion, Goranson advocated the need 
  for 3D thermal modeling of the vacuum vessel and neighboring structure to 
  address cooldown between pulses. This would be a new task not included in the 
  current work plans. ACTION: Goranson develop and propose 
plan.
 
2. Modular Coil Schedule 
Risks
  - CAD modeling of the MCWF is making progress and, it is 
  hoped, will be resolved this week. The T. Brown approach is working well. 
   The Williamson approach is still being pursued. The Hargrove approach 
  has been dropped. Hargrove is working on “tool solids” modeling needed by J.P. 
  Pattern.  It is anticipated that the Brown approach will be able to model 
  all three MCWF’s, without interferences. This has not been demonstrated yet 
  but it is hoped to be completed this week. 
  
 - Structural analysis remains an issue, but resources 
  have recently been added to the global modeling task (H.M. Fan) and we expect 
  to make progress with simpler approaches in parallel, and have a story by the 
  FDR. The plan for documenting all needed load cases still needs to be fleshed 
  out and incorporated in the WAFs. ACTION: Williamson.
 
  - In a separate discussion, Williamson advocated making 
  fuller use of the prototyping activities to develop the process for accurately 
  winding the coils. Multiple metrology approaches may need to be tested to 
  determine the best approach for use in coil production. ACTION: Williamson 
  follow up with metrology and coil winding groups to ensure needed tools are 
  being procured and to develop the plan.
 
3. Technical Risks
Wayne led a discussion of critical 
technical issues and updated a tracking list which has been developed. 
Highlights not already covered:
  - We do not yet have an adequate R&D plan to develop 
  the reference material properties and design criteria, and resolving cure 
  strain inconsistencies. ACTION: Brad, develop the SOW for the R&D program. 
  
  
 - We need the magnitude of field arrors from structural 
  steel around the machine. ACTION: Wayne follow up with Brooks and Strickler to 
  determine responsibility.
 
4. 
 CD-2 preparations
  - The Change Control Board met on 12/8 to review changes 
  to the GRD. A handfull of issues requiring follow-up was identified and 
  assigned. It is expected that the GRD changes will be approved before the 
  holidays. 
  
 - The PDR, PBR, and EIR disposition plans are out for 
  review and response by the WBS managers by Friday, Dec. 12. ACTION: Neilson 
  follow up. 
  
 - The ECP documenting changes from the PDR baseline to 
  the CD2 baseline will incorporate review responses and any changes to the DOE 
  funding profile. Project-initiated changes resulting from the WAF planning and 
  updating processes will, as a rule, not be incorporated into this ECP but 
  swept up at the next Lehman review. Exceptions will be considered 
  case-by-case. They may entail calls on contingency.
 
5.  Next SIT Meeting: Monday, December 15, 2003 at 
1:00 p.m. (Note special time.)
Summary by:
Hutch Neilson