Minutes of the NCSX-DOE IPT Meeting on January 15, 2003
On the teleconference:
Warren Marton (DOE-OFES), Greg Pitonak (DOE-PG),
Chuck Finfgeld (DOE-OFES), Gene Nardella (DOE-OFES), Jim
Lyon (ORNL), John
Schmidt (PPPL), Hutch Neilson (PPPL), Wayne Reiersen (PPPL),
Ron Strykowsky,
and Bob Simmons (PPPL).
Topics of Discussion:
(1) DOE Status - Warren Marton and Greg Pitonak
(a) The CR has been extended to the end of January. No firm projections on
what will happen then. For planning purposes, the Project
continues to
assume a March 1st Project Start. The current
"baseline" is the $73.5M total
cost/June 2007 schedule.
The baseline will be updated for the PDR/EIR to
incorporated the effects of the Continuing Resolution,
accounting changes
(e.g., safeguards and security costs at PPPL) and any
technical changes
resulting from design and R&D activities. Generally, the
Project has
continued to optimize the conceptual design, including some
new concepts and
evaluation of some additional details. The value of these efforts to the
Project is a confirmation of performance improvements,
refinement of risks,
and greater visibility of costs.
(b) The guidance for the FWP from DOE should be issued
within the next
several weeks. PPPL
should update the overall funding project profile (as
compared to that in the AEP) => less MIE project funds in
FY2003 due to CR
and more funds needed in FY2004 and out years?
(c) Warren questioned whether there were sufficient funds remaining
in the
PPPL and ORNL contracts in light of the extension of the
CR. Both Hutch and
Jim indicated that they believed that there were sufficient
funds to last
through February, but would confirm this. ACTION:
Ron Strykowsky and Jim
Lyon confirm adequacy of funding and get back to Warren.
(2) Project Status -
Hutch Neilson
(a) Technical progress - Hutch indicated that the design
update is
proceeding based on the M50 coil design adopted just before
the holidays.
He confirmed that the M50 design would be the basis for the
PDR. The
advanced conceptual design is progressing well with internal
project reviews
of key issue areas (e.g., poloidal break, Cu cladding,
tolerances, etc.)
scheduled within the next several weeks.
(b) Prototype Contracts - The proposals for the modular
coils winding form
prototype have been received - a total of 5 proposals were
received and a
great deal of evaluation and interaction with the bidders
has occurred. It
is anticipated that the two modular coil contracts will
ready to be placed
in late January. The
vacuum vessel proposals are due in late January. DOE
has requested an issue paper from the Project indicating the
need to award
these prototype contracts before the end of the CR. It is anticipated that
a draft will be provided later this week.
(3) NCSX Review Discussions - Warren Marton, Hutch Neilson,
and Greg Pitonak
(a) PDR - Hutch has coordinated the dates of the PDR to be
the week of June
23rd - nominally June 24-27. Warren has discussed with Dan Lehman whether
his group wants to take the lead in organizing this review
and Dan has
indicated that he would not become actively involved until
such time that
the Project is ready to start construction. Accordingly, OFES organize the
review charter and members in consultation with the Project
and PG like we
did for the PVR.
John reminded all that the internal PPPL requirements for
PDRs will also have to be satisfied and that this will have
to be taken into
account in the makeup and conduct of the PDR. While the PDR will
technically focus on the VV and modular coils, the entire
updated cost and
schedule estimates will also be addressed in preparation for
the EIR.
(b) EIR and CD-2 - The Project is tentatively planning for
the EIR in July
and CD-2 in August.
Due to the continuing CR, the OECM schedule for EIRs
may be slipping.
ACTION: Greg and Warren interact
with OECM to ensure
that a summer EIR date is scheduled.
(c) PCS Review - Greg is coordinating with DOE and other
potential
reviewers. Current
thinking is sometime in late February or early March
(work around FWP schedule).
The next IPT meeting will be Tuesday, February 11th, at
11:00 am.
If you have any corrections, please contact me.
Bob S.