WBS 1 Telecon

 

11 June 2003

Agenda

Critical path issues and near term tasks (WR)

Reports from CTD (JC)

Progress on keystoning tests (JC)

Sapper re W7-AS - What did we learn? What next? (JC)

Decision strategy for conductor parameters (gauge, serve, twist pitch, insulation, cross-section, single/multi) (JC)

Task description for suppliers (PH)

modeling the "wings" of the shell

optimizing poloidal break design