Summary of WBS 4 Cost Review Meeting of Wednesday, June
18, 2003
Attendees were S. Ramakrishnan, L.Dudek, M. Williams, C.
Neumeyer, R.Strykowsky, W.Reiersen, M.Zarnstorff, and H.Neilson.
Raki's updated estimates were discussed. They are based on
the CDR requirements, updated to waveform data issued by Wayne in April, 2003.
The estimate was $7,542k, an increase of $899k over the current baseline. We
discussed the reasons for the increase and possibilities for cost reduction.
The following decisions and assignments resulted:
1. WBS 432, D-to-C-site DC Systems: Raki proposed a 2-wire
design for all circuits. However, some of the circuits can be stacked (not the
modular coils) and still satisfy voltage test requirements. This would reduce
the number of cables. It was decided to modify the stacking to the extent
possible to reduce Day-1 cost. ACTION: Raki revise the estimate.
2. WBS 433, D-Site DC systems. New firing generator and
fault detector circuits were proposed, which would update to modern technology
and improve equipment protection. However, it was decided that the project
would live with the existing circuits through first plasma. An upgrade after
first plasma was recommended as a benefit to both NCSX and NSTX.
ACTION: Raki revise the estimate.
3. WBS 412, Experimental AC power. Apparent estimate growth
has already been resolved. ACTION: Raki revise the estimate.
4. WBS 446, Ground fault monitor. It was agreed to remove it
from the baseline, as recommended by Raki.
5. WBS 46 (new), FCPC Modifications. It was agreed
that these costs should be budgeted under WBS 4.
ACTION: Raki follow-up with J.Chrzanowski on estimates.
ACTION: Ron find out if this scope is already budgeted
somewhere, e.g., in WBS 7.
6. It was decided that further MIE scope reductions should
be pursued by exploring reductions in the number of Day-1 circuits. The physics
team (N. Pomphrey) is looking for acceptable equilibria.
ACTION: Mike Z. and physics team develop candidate design
basis equilibria with simpler circuits.
ACTION: Raki develop simpler configuration once requirements
are received.
7. ACTION: Raki submit updated estimates to Ron by Monday
June 23. (Except #6 which will take longer.)
Possibilities for accelerating WBS 4 scope were discussed.
It was decided we should try to expedite the design work in order to position
the project to be able to perform construction work whenever money becomes
available to do so. Additional resources needed:
1. Electrical design support this year. ACTION: Mike W.
follow up.
2. $35k of M&S to fund structural design contract.
(probably next year)
3. $400-ish K of M&S to install the towers. (Next year)
Summary by:
Hutch Neilson