Summary of NCSX System 
Integration Team (SIT) Meeting of Monday, October 27, 2003
Attendees 
were  Schmidt, Strykowsky, Reiersen, Nelson, and Neilson.
1. 
Assessment of PDR Recommendations
We had a discussion of the PDR 
recommendations focusing on the following subset:
  - Comment in Ch. 2 (no number), WBS 14: concern about 
  the short time between MCWF prototype delivery and release of production 
  contracts. Preliminary assessment: agree. Add about a month to the 
  schedule.
 
  - Recommendation 3-3, 350 C bakeout of the VV, WBS 
  12:  Simplifying the PFC design is a benefit.  We considered this 
  approach a long time ago and rejected it for diagnostic reasons.  In a 
  follow-up discussion with Dave Johnson (10/27), he is concerned about windows, 
  fibers, and temperature control of re-entrant diagnostics if everything goes 
  to 350C. The magnetic diagnostics are not a concern.  At this time, we do 
  not yet know what impact this change would have on the design process. Paul 
  Goranson is developing the complete list of issues that would have to be 
  addressed. We will review Paul’s list later in the week. Preliminary 
  assessment:  First find out (via Paul’s analysis) if this is a major 
  setback to the design schedule, in which case we don’t want to do it. If not, 
  then we have to do more analysis of costs and benefits to decide.
  - Recommendation 4-2, pre-assembly of each type of 
  modular coil shell joint, WBS 18.  Concern (per follow-up telecon 
  with Ray Johnson) is that there is non-negligible risk of errors entering and 
  surviving through design, fabrication, and inspection.  A fit-up test 
  before making a large investment in coil windings is seen as a prudent step. 
  We agree, except we would not hold up winding the coil, so we would check, for 
  example, the first wound Type C coil with the second bare type C winding form. 
  Ray is not concerned about reproducibility, but we are not so sure.  Phil 
  Heitzenroeder argued (afterward) that the whole fit-up exercise is unnecessary 
  if our QA and metrology are adequate. Preliminary assessment (prior to 
  Phil’s input):  accept as described above, so as not to delay the winding 
  process. 
 
- Recommendation 4-3, full-size mockup to demonstrate 
  assembly of modular coil triplets around the VV, WBS 18 (and 12): 
    We agree that this would be valuable to develop the process 
  because the clearances are tight and controlling the trajectory might be 
  difficult. It was  argued that the the VV mockup should be a rigid part 
  and could be used to prototype other VV-related concerns, such as welding the 
  field joint and dimensional stability, so we talked about getting a 60-degree 
  sector from one of the suppliers.  Preliminary assessment:  a 
  full-size mockup is already in our plans, but not clear if  it goes far 
  enough, so we may need to add more budget.  Regarding a real 60-degree VV 
  prototype, we will find out the cost from the suppliers and weigh against the 
  benefits. 
 
- Recommendation 3-5, expedite prototype VV sector to 
  assess tolerance build-up and dimensional stability; and provide for staged 
  delivery, WBS 12. Those on the call favor staged delivery of the three 
  sectors as it would offer more schedule flexibility.  (As an aside, we 
  also favor letting the suppliers attach the cooling tubes instead of us doing 
  it, which requires nailing down the magnetic diagnostics interfaces in 
  advance.)  We don’t want to pay for a 4th segment, but we also don’t want 
  to make any design or process changes after the first segment. The question 
  is, is our 20-degree prototype adequate to resolve the concerns about 
  tolerance build-up and dimensional stability? If not, would a single 60-degree 
  prototype shell with a minimum of ports be justified?  Preliminary 
  assessment:  we agree on staged delivery but are not yet convinced that 
  our existing prototyping plans are inadequate to address the issues raised 
  here.  Further investigation is needed. 
 
- “Little-ticket” recommendations, such as: 2-1, 
  modular coil composite R&D; Ch. 2 comment on controlling the 
  cable-compacting process & use of lubricants; 3-2, automated welding of 
  field joint; 3-4, aerogel insulation; 3-7, cryostat penetrations;  5-1, 
  external vaporizer and humidity sensors; 7-1, ground-fault monitor; and so on. 
   There are of order 10 of these, costing of order $20-$50k, plus 
  contingency, so these items are expected to come to ~$500k or so. 
    Wayne is following up with the WBS mangers to improve estimates. 
  Under a fixed funding profile (and resource limitations), more cost can mean 
  schedule stretchout. 
 
- Comment that “schedule is tight”  can be read as an 
  implicit recommendation for more schedule contingency, say 2 
  months.
 
- Recommendation 12-2, Allowing time in the schedule 
  for bottoms-up cost estimating.  Recognizing this could add, say, 1/2 
  month per year for the next four years, or 2 months.
ACTIONS
  - Wayne, mark up disposition plan with rough cost and 
  schedule impacts as input to Ron (by Tuesday early afternoon). 
  
- Ron, perform a what-if schedule analysis to determine 
  C&S impact based on Wayne’s markup (by Weds. p.m.) 
  
- Hutch arrange conference call Weds. p.m. or Thurs. a.m. 
  to update Rob and Rich on PDR assessment.* 
  
- Brad, update R&D and analysis plans, taking into 
  account PDR recommendations, new conductor design, latest understanding. 
  Coordinate with conductor procurement. 
  
- Brad, work with Paul to clarify issues with 350C VV 
  bakeout. 
  
- Brad, work with Paul on risks/benefits of staged 
  delivery of VV segments. 
  
- Wayne, develop PDR recommendations disposition plan, to 
  be available in time for DOE review. Also respond to committee “comments” as 
  appropriate.  Note that final report wording differs from closeout 
  briefing in some places.
*Agenda 
for telecon with Rob, Rich, et al. later this week.
  - Cost & Schedule impact assessment of PDR report.- 
  Hutch, Ron, Wayne 
  
- Plan for developing PDR issues disposition plan, dealing 
  with it at the DOE review, and incorporating it into the baseline.– Hutch 
  
  
- Updated R&D and analysis plan (depending on 
  interest)- Brad 
  
- Details of disposition plan (depending on interest)- 
  Wayne
 
2.  Updating the 
Baseline.
Conclusions of the discussion that took place mostly after 
I left (please correct):
  - The GRD was approved and placed under configuration 
  control several months ago. An ECP is in preparation to formally update to the 
  revision that was issued at the PDR.  It should not need to be approved 
  by DOE, I don’t think, since we do not yet have a DOE-approved baseline. 
  
  
- At the PDR, we presented the “PDR baseline”. 
    Since we have a comprehensive and self-consistent package of 
  documentation for the PDR baseline, the appropriate documents should 
  presumably now be placed under configuration control, in accordance with the 
  configuration management plan. 
  
- Between the upcoming DOE reviews and CD-2, the baseline 
  is expected to be updated to capture the results of the PDR and the November 
  DOE reviews.  An ECP should be executed to go from the PDR baseline to 
  the CD-2 baseline. The PDR documentation plus this ECP equals the CD-2 
  baseline, which DOE will approve.
3.  FY-04 Work Planning and Authorization 
(Ron)
  - Master schedule will be used as a placeholder for WBS 4 
  WAF until Raki returns from vacation. 
  
- WBS 15 (coil structures) needs input from Phil, now 
  returned to the lab.
ACTION:
  - Ron schedule October job status meetings for Thurs., 
  Nov. 6. Work around QPS IPT meeting at 10 am.
 
4.  Planning for DOE Reviews (Hutch)
  - Draft agenda was issued for comment. Comments so far: 
  Assembly & Metrology Overview talk will be presented by Mike Cole. 
   Vacuum vessel and modular coil talks will need to be shortened. Talks 
  should be sure to adequately cover basis of estimate and contingency for all 
  systems. 
  
- WBS managers can expect to be contacted by Lehman review 
  committee members. Copies of all correspondence should be sent to Reiersen, 
  Nelson, Strykowsky, and Neilson. 
  
- Document preparation responsibilities were updated. 
  Issues are Start-up Test Plan (Gentile, Simmons) and drawings (Brown). 
    ACTION: Wayne follow up.
 
DOE Review Preparation Schedule
Nov. 6,  October job status meetings. 
  
Nov. 7,  All-hands kickoff meeting. (1:30 ok?)
Nov.  10-14, 
   Dry runs (afternoons.  mornings if needed)
Nov.  14, COB. 
  Final presentations to Pamela for copying and 
posting..
5.  Next 
SIT Meeting: Monday, November 3, 2003
Summary by:
Hutch 
Neilson