Summary of NCSX System Integration Team (SIT) Meeting
of Monday, August 23, 2004
1. Project
Re-planning for CD-3 and preparation for Sept. 1 Lehman Review
(Hutch)
- Good progress has been made
in project re-planning to accommodate VVSA and MCWF cost increases. Projected
budget contingencies appear to be adequate unless there is erosion of the
savings identified to date.
- Schedule improvements to
offset the 5-month delay in delivery of the last MCWF still look marginal.
We do not yet have a crisp story. More work is needed to
understand the critical path schedule from delivery of the last MCWF to First
Plasma and identify improvements. Action: Ron convene a meeting on
8/24 at 11:00 to review and improve the schedule.
- We do not yet have a crisp
assessment of the risk associated with fracture life of the MCWF. Tests
are planned to determine where the NCSX alloy falls in the range between the
optimistic and pessimistic data bases in the literature. Since the
results will not be available before the review, we need to show how we can
live with the worst-case outcome. Responsibility:
Wayne
- Analysis results using a
more accurate structure model may provide some clarification this week.
Brad.
- What spectrum of pulses
would be achievable in the worst case? For example: 30,000 at 2T,
100,000 at 1.7T?
- The testing and analysis
activities needs to be in the budget. Wayne and
Ron.
- How much of the VVSA and
MCWF price increase is due to materials price increases, ball-park?
Action: Phil.
- What is the risk that the
schedule will be impacted by long lead times for delivery of key materials
such as inconel? Action: Phil.
2. Gain schedule
improvement by using the prototype coil? (Phil et al.)
- It was proposed that we
consider machining the prototype C casting for use as a production winding
form. The issue is whether the prototype design is sufficiently similar
to the final design so as not to introduce field errors due to
non-stellarator-symmetric eddy currents. The design of the production
forms differs from that of the prototype due to specification changes made by
the project during final design and to possible changes that could result from
changes in the manufacturer’s tooling. Some modification of the
prototype casting would be necessary even in the best case.
- It was concluded that we
will be able to judge whether the remaining Type C castings and the prototype
are sufficiently alike once we see the new pattern design, which we expect to
be submitted for our review this week. We will take up the question at that
time. Responsibility: Phil
3. Project
Control (Wayne)
- The re-planning and
vacations have caused our plans to diverge considerably from our baseline. It
was recommended that the ECP implementing the new plan be processed
expeditiously, so that August performance can be statused against the new
baseline. Action: Wayne work with Ron.
- August status meeting will
be about September 10.
4. Next SIT Meeting: to be
announced.
Summary by:
Hutch Neilson