Summary
|
1.
Producing the FDR Deliverables
Several meetings were held in the past two weeks aimed at identifying
key reviews and deliverables. Status was reported by Reiersen and Nelson.
April
2, FDR of twisted racetrack coil (TRC)
April 15, Fabrication Readiness Review of TRC
May 19-20, FDR of the Production Modular Coil Winding Forms (All 3
types)
July 7, Fabrication Readiness Review of the Modular Coil Prototype
Dec. 15, Fabrication Readiness Review of the Type C Production Modular
Coil
May
19-20, FDR of the Vacuum Vessel Subassembly
by March 31, 2005, FDR of VV hardware (heating/cooling
distribution, insulation, supports)
t.b.d.,
Weld joint R&D Plan, Goranson
Feb. 27, VV port configuration, Part II, Cole
Feb. 27, Racetrack coil test plans, Nelson, Gettelfinger.
Mar. 3, Type A & B Modular coil casting models for
solidification analysis., Williamson
Mar. 10, Structural Design Criteria and Material Allowables, Zatz
Mar. 10, EM loads and fault conditions, Strickler, Fan
Mar. 10, Eddy Currents and disruption loads, Brooks
Action: Identify peer review chairs for as many of the reviews as
possible. (Reiersen, Nelson)
-
Analysis
tasks.
-
Vacuum
vessel analyses: See WBS 12 meeting notes of 2/12 on Engineering
Meeting Records page. Tasks are in the process of being estimated,
assigned, and scheduled.
-
Modular
coil analyses: draft plan has been issued. Tasks are in the
process of being estimated, assigned, and scheduled.
-
FDR
Deliverables. VVSA and MCWF deliverables lists for the May FDR
were issued by Nelson, addressing analyses, manufacturing development,
requirements, configuration models, product specifications, drawings,
ICDs, and other documents. Drawing lists are still coming together.
-
Strykowsky
reported that the revised plans are being incorporated into the ECP-5
baseline. So far, the impact on resource needs is beneficial, due to the
spreading of tasks over a longer time. The ECP-5 baseline will be
issued these week.
Action:
further changes to be incorporated into the ECP-5 baseline should be
submitted to Ron by 2/27.
2.
Project Control (Ron)
-
CCB
to approve ECP-5 will be held on or before March 5. ACTION:
Simmons to coordinate.
-
February
status meeting will be March 5. Ron will arrange. Status
will be reported against the ECP-5 baseline. Data will be
submitted to Federal Project Director for input to PARS system.
3. Final Design Review plan
-
The
VVSA/MCWF Final Design Review will be May 19-20 (Weds.-Thurs.)
-
A
draft plan addressing charge, input deliverables, output deliverables,
review panel members, and review agenda was discussed. Action:
Neilson update the plan based on discussion.
-
A
FDR web page will be set up similar to the PDR and other web pages.
Action: Pamela.
4. Critical Technical Issues (Wayne)
-
The
critical technical issues list has been updated and posted on the
Engineering web page. Good progress is being made in resolving
critical issues. Several have been resolved recently.
-
Two
new issues were added:
-
Electropolish
the vacuum vessel? Decision needed based on cost vs benefit,
by Feb. 27. Responsibility: Neilson
-
Who
owns the port adapters beyond the first flange, VV or Diagnostics?
It was decided that the answer is probably Diagnostics for
those ports whose first flange is inside the cryostat. The
topic may be discussed as an add-on to the VV port configuration,
Part II peer review, but some advanced preparation by the affected
parties is. Action: Mike and Brad coordinate the necessary
discussions and preparations.
The
resolution will be documented via an ICD between WBS 12 and 3. Action:
Simmons.
5. Next SIT Meeting: Monday, March 1, 2004 at 11:00 a.m.
Summary by:
Hutch Neilson
|