From: Hutch Neilson [hneilson@pppl.gov]
Sent: Tuesday, January 13, 2004 1:20 PM
To: Hutch Neilson; Michael Zarnstorff; Wayne Reiersen; Bob Simmons; Larry Dudek; Ron Strykowsky; Brad Nelson; John Schmidt; Jim Lyon
Subject: Summary of NCSX SIT Meeting of 1/12/04
 Summary of NCSX System Integration Team (SIT) Meeting of Monday, January 12, 2004

1.  Critical Issues  (Wayne)
The critical issues list will be used for week-to-week risk management by the SIT. Three categories of issues are defined:
  1. Requires weekly SIT attention until there is a mitigation plan
  2. Mitigation plan is in place, actions to resolve the issue are under way.
  3. Issue has been resolved, listed for historical reference.

Among the Category 1 issues, the following were highlighted:

Among the Category 2 issues, the following was highlighted:

2.  CD-2 preparations
New developments:

A revised CD-2 preparation schedule was developed (attached). Key dates:

A concern was raised about the plan to submit an ECP (ECP-004) which will include only a subset of the changes that the project is aware of at the time of submission.  This is being done to limit the scope of ECP-004 to changes resulting from review recommendations, DOE-directed changes in scope and CD-4 definition, and DOE funding profile changes which have been agreed to with OFES. The concern is that the project could be faulted for omitting other changes that have come to light in the normal course of execution since the PDR baseline was established. This concern is being addressed by the plan to produce a second ECP (ECP-xxx) to capture all remaining changes needed to bring the baseline fully up to date in a timely fashion. I have discussed the concern that was raised and our plan with Greg Pitonak, who concurs in our planned course of action.

3.  Next SIT Meeting: Monday, January 19, 2004 at 11:00 a.m.  Wayne to issue announcement and chair the meeting.

Summary by:
Hutch Neilson