From: Hutch Neilson [hneilson@pppl.gov]
Sent: Monday,
February 16, 2004 3:48 PM
To: Wayne Reiersen
Subject:
Summary of NCSX SIT Meeting of 1/26/04 FOR MEETING RECORDS
I noticed this was missing from the meeting records page.
Hutch
Summary of NCSX System Integration Team (SIT)
Meeting of Monday, January 26, 2004
1. Critical Issues
(Wayne)
The up-to-date critical issues list is posted
at:
http://ncsx.pppl.gov/NCSX_Engineering/Management/Critical%20Issues/CriticalIssuesStatus.xls
The
following critical issues were discussed:
- ID #82-2. System Analysis Tasks. The list of
needed tasks and task leaders has been developed. The cost and schedule are
being worked. The cost to complete needed FY-04 tasks may exceed
original estimates. ACTION: Wayne to incorporate plans and updated
estimates into FY-04 WAFs by Feb. 6.
- ID #82-2. Vacuum Vessel shell geometry.
Physics needs the final PFC surface geometry to evaluate adequacy of
plasma-wall gaps. However, the geometry may yet have to be modified to resolve
the field-period assembly interference issues. RESPONSIBILITY: Brooks.
- ID #12-2. Vacuum Vessel Port Geometry. It was
decided to hold a peer review of the port arrangement, inviting all the
stakeholders (e.g. Diagnostics, ICRF) to attend and “speak now or forever hold
your peace,” Brad has scheduled a peer review for this Thursday, to be chaired
by Larry Dudek.
2. Job
Status report
- It was noted that the performance indices for April
through December, 2003, were SPI=0.95, CPI=0.96. These remain above the red
flag threshold of 0.90 but have slipped significantly since the preceding
month from 1.00 and 1.01, respectively.
- It has been agreed that future-month plans and estimates
of current-year WAFs can and will be modified to keep them current
without requiring an ECP. This will ensure that month-to-month performance is
tracked against a relevant baseline.
- The January job status meeting will be held Friday,
February 6. Ron will issue the call for input and arrange the
meeting.
3. Planning for next
Lehman Review and CD-3
Hutch met with DOE personnel on Monday afternoon
to discuss the review requirements for CD-3. The conclusions were:
- The next NCSX Lehman review will be June 8-9 or 9-10.
Note that this follows the Final Design Reviews of the modular
coil winding forms and vacuum vessel, scheduled for about May 20.
- The June Lehman review will have two objectives: 1)to
serve as the Independent Project Review required for CD-3, and 2)to serve as
the next semi-annual SC project review of NCSX addressing overall project
performance.
- CD-3 approval will be targeted for July, in order to
support the project’s schedule for awarding production contracts starting in
August.
SIT members are asked to
report any conflicts with these dates as soon as possible.
4.
CD-2 preparations
- The CD-2 baseline was revised to incorporate some of the
larger FY-04 cost growth items into the base estimate. These items totaled
about $1.2M and were covered by reducing contingency. Contingency stands at
26% of work to go. A larger number of smaller puts and takes affecting
nearly all WBS elements, but with a smaller total, will be covered in the
follow-up ECP.
- The Project Execution Plan has been updated to
incorporate the revised cost and schedule baseline, new CD-4 criteria, and
project objectives narrative. It has been issued for signature.
Responsibility: Bob
- Documentation supporting CD-2 is posted at
http://ncsx.pppl.gov//Meetings/PDR/CD2/CD2.html.
- The EIR tracking log has been updated to reflect
additional completed items.
- Greg Pitonak’s draft presentation and the CD-2 approval
memo has been issued for comment.
- The CD-2 ESAAB, to be chaired by Anne Davies, is
scheduled for Feb. 3 at 3:00 p.m. All preparations are on
track.
5. Next SIT
Meeting: There will be no SIT Meeting on February 2. The next meeting
is scheduled for Monday, February 9, 2004, at 11:00 a.m.
Summary
by:
Hutch Neilson