Summary of NCSX System Integration Team (SIT) Meeting of Monday, July 19, 2004

1.    WBS 1 Re-planning activity and CPI/SPI improvement (Wayne)
Re-planning input for the major work packages has been received. A top-down schedule is being developed toward the milestone of starting to wind the first production modular coil in mid-January. There are three major activities, all of them close to the critical path:

An ECP is being developed to bring the performance measurement baseline in line with the new plans. In addition the ECP must address the declining performance indices for the July close. Actions regarding the re-planning ECP (Bob, Ron):

2.   Prototype MCWF processing (Wayne et al.)
We discussed a proposal by Wayne to terminate processing of the prototype MCWFs once the production proposals are received. It was argued that continued work on prototypes thereafter would be of little value but high cost. Brad recommended finishing the poloidal break.  He pointed out that they could be used for assembly practice (e.g., testing the C-C mating) if completed. Phil stated concerns that the fracture properties testing effort is going slowly, and neither supplier has submitted complete properties data. We concluded the following.

3.   Metrology critical issue (Wayne)
Wayne announced the project’s metrology core team:  Art Brooks will be project’s expert resource, consistent with his technical assurance responsibilities. Mike Cole will lead design efforts. Steve Raftopoulos will lead field implementation.  All will attend the W7-X Metrology Workshop in August. They have been invited by the W7-X team to serve as reviewers.

4.  Next SIT Meeting:  Monday, July 26 at 11:00 a.m. EDT.

Summary by:
Hutch Neilson