Summary of NCSX System Integration Team (SIT)
Meeting of Monday, June 14, 2004
1. Addressing MCWF
and VVSA Procurement Schedule Risks
- VVSA (RFP to be
issued 6/16).
- Spec: with Goranson;
comments being incorporated.
- SOW: in signature process
- Drawings and models:
those sent last week should be in approval process with Brown and Parsells.
The last group were expected to be sent from ORNL to PPPL today.
- RFP: Phil will
follow up with procurement. The evaluation criteria will be reviewed one
last time to be sure it is what we want.
- MCWF (RFP to be issued
6/25).
- Drawings and models: Brad
forecasts the full package will be sent to PPPL 6/23. He will push to
ship the Type C package sooner. It was decided that the MCWF drawings
do not need to be approved by the weld engineer.
- Spec and SOW: Being
modified to accommodate FDR recommendations. Main issue is the fracture
issue, which may require enhanced inspection requirements, alloy chemistry
control, and test samples. Action: Phil follow up with suppliers
and propose modifications.
- Strategy: ask for
proposals to be submitted July 23, even if prototype fabrication is not
complete. Cost risk is judged to be outweighed by cost of accepting a
schedule delay. To mitigate risk of schedule slippage due to procurement
delays, ask both teams to start producing a new R&D casting, built to
the final specs. One team will be asked to build a Type C, the other a
Type B. The additional workscope will extend through the casting
phase, with only the initial steps authorized at first. The production scope
will consist of finishing this R&D form and producing the remaining 17
forms. The requested delivery schedule will address the need to maintain the
required production schedule and to have one coil of each type available for
assembly testing when field period assembly tooling becomes available.
- Split-order fallback
options were discussed. There are a range of possibilities in the event the
production proposals are unsatisfactory in price or
delivery.
2. Critical Issues (Wayne)
The
critical issues list has been updated an posted on the web. New items
include:
- Modular coil cooling.
Workshop was successful but now a plan is needed. Action: Brad.
- MCWF fracture issue.
Action: Phil.
- MCWF delivery schedule.
See above.
- Commodities cost risks.
Option of project assuming the risk of material price fluctuations.
- Final Design Closeout.
Action: Wayne to finalize plan and post.
- Shear carrying capacity of
modular coil windings.
3. Cost and schedul performance
(Ron)
- CPI slipped to 0.94 in June
due to MCWF final design variances, winding R&D, and design integration.
Production of final design deliverables is behind schedule.
- SPI slipped to 0.93 in June
due to slippage in the prototype schedules, especially
MCWF
4. Next IPT Meeting:
t.b.a.
Summary by:
Hutch Neilson