Summary of NCSX System Integration Team (SIT) Meeting
of Monday, June 28, 2004
1. MCWF and VVSA
Procurement
- The Engineering team is
congratulated for having issued the VVSA RFP on June 24, an important
milestone for the project.
- There was a discussion
concerning how long the prototype machining activity should continue.
The purpose of this activity is to provide the suppliers with experience
that can benefit their production proposals. Once final proposals are
submitted, namely their so-called “best and final offers” prior to source
selection, the activity will have served its purpose. Therefore it was decided
that the prototype machining activities will continue until best and final
offers are submitted.
2. Monthly Briefing for DOE, June
30
- The Project team will brief
DOE on June 30, and monthly thereafter, as a new feature of the monthly
reporting process. The June 30 briefing will focus on procurement issues
and project responses to the recent Final Design Review and Lehman Independent
Project Review.
3. Critical Issues
The following
items from the critical issues list were discussed:
- 14-10, Service life of the
MCWF (fracture limitations). The project is resolving this issue as
follows:
- The spec has been
modified to require a higher level of radiographic inspection in the
critical, high-stress areas. Internal flaws larger than a certain critical
size will have to be repaired.
- The suppliers are
required to “bias” the design of the gating system, using their flow
solidification analysis, so as to promote high casting quality in the
critical areas.
- The suppliers are
required to provide an expanded materials properties data set, including
transverse and longitudinal properties, modulus, and charpy tests. They will
test 3 samples, equally spaced around the circumference from each casting.
- The project is conducting
fracture tests on samples of each supplier’s alloy. The samples have to be
machined to the proper configuration, then tested. Phil is working
with vendors to determine price and delivery for machining and testing.
Time scale is expected to be of order 1 month.
- The project is continuing
crack growth analysis to determine what to put in the criteria document as a
failure criterion. This is being led by ORNL (Kevin Freudenberg) in
collaboration with Len Myatt. Time scale is expected to be of order 4-6
weeks.
- 12-3 and 81-2,
Completion of MCWF final design. The WBS 1 team decided to modify
the poloidal break design based on supplier feedback. The prototype drawings
and models are being updated. Checking of drawings is still in progress.
The RFP is expected to be issued this week (by July 2).
- 14-9, MC winding pack
cooling. Bids for the clamps have come in lower than expected, reducing
cost growth risk from $250k to $80k. June 10 workshop identified a
number of improvements in the cooling design. Further improvements are being
identified. Cost growth risk of $500k identified at Lehman review is
coming down, but not yet quantified. The technical issues of modular
coil winding are a continuing focus of the weekly WBS 1
meetings.
4. Cost and schedule
(Ron)
- WBS 1 work activities have
diverged sufficiently from the WAFs that it was decided to re-plan the
schedules through about December, 2004 at this time, in order to re-establish
a valid baseline to report against. The time horizon covers the period
in which we will complete preparations for winding the modular coils, which we
are aiming to start in December.. The re-planning activity has begun and
is to be completed in the next few days.
- June status meeting is
tentatively targeted for Wednesday, July 7 but may be postponed a few days to
complete the re-planning.
5. Safety
(Hutch)
- We discussed some
safety-related incidents that have occurred recently at PPPL, and their
implications for NCSX.
- Our safety management
approach must target reductions across the entire range of accident severity,
from the relatively minor (cuts, muscle strains) to major injuries.
- We need to emphasize
observance of signs, barriers and other measures designed to keep people out
of dangerous areas or take proper precautions when in those areas.
- As a follow-up to the SIT
meeting, Erik Perry provided the following information concerning the safety
issues associated with access to NCSX test cell: The NCSX test cell
is a construction area. When ropes are in place, they definitely mean
“do not enter” and must not be crossed. The ropes are taken down
whenever there is not a reason for them to be in place. Safety shoes are
required due to the nature of the hazards in that area. Any time access is
required for a specific occasion, one should contact Erik, who will make every
effort to accommodate, even on short
notice.
6. Next SIT Meeting: t.b.a.
(Note: there is an IPT Meeting scheduled for Tuesday, July 6, at
11:00.)
Summary by:
Hutch Neilson