From: Hutch Neilson [hneilson@pppl.gov]
Sent: Monday, May
03, 2004 9:35 PM
To: Hutch Neilson; Phil Heitzenroeder; Mike
Zarnstorff; Wayne T. Reiersen; Bob Simmons; Larry Dudek; Ronald L. Strykowsky;
Brad Nelson; John Schmidt; Jim Lyon; Pamela Hampton; James H.
Chrzanowski
Subject: Summary of NCSX SIT Meeting of 5/3/04
Summary of NCSX System Integration Team (SIT) Meeting of
Monday, May 3, 2004
1. Critical FDR
issues
Update on critical issues
identified at the April 26 SIT meeting. Corrections or fine-tuning of
assessments requested.
- Modular coils structural performance: Major
progress last week: tension data for the potted conductor were obtained;
conductor performed well in the first cyclic fatigue test, and there were
first analytical results from the model where the winding pack moves with
respect to the structure. There are still gaps in the materials
properties for the cable conductor. There is some debate as to whether the
correct strain range is being used in the conductor fatigue tests. The
analysis confirmed expectations that the MCWF “wings” need extra support and a
design solution is being drawn up. Assessment: margins are not
everywhere as wide as we would like, properties data is not as complete as we
would like, but we have enough to demonstrate that the design works at the
FDR. Expect a successful FDR, but some chits to complete the materials testing
and some analysis tasks
- Vacuum vessel shell deflections: Some ideas
were examined last week for reducing the calculated 1/4-inch deflections in
the VV. The largest deflections are at the end of a port. A local
“patch” stiffener did not help much. Local ribs introduce fabrication risks,
deemed unwise this close to the FDR. Lashing the ports together is an
idea but there is no time to evaluate it. The deflection of the ports
does not appear to be a real problem so it was decided to simply allow it to
flex. Assessment: vacuum vessel in good shape for FDR.
- Modular coil cooling concept: A position and
plan was adopted by the SIT:
- The baseline winding pack design works but there are
concerns about its fabrication cost and schedule, mainly having to do with
the complexity of fabricating and assembling the cladding and chill plates.
This is recognized by the project as a risk and needs a mitigation plan.
- The requirements for the FDR are satisfied: a
modular coil design that works, including an MCWF specification that is
ready to release for fabrication. Mitigating the winding cost and
schedule risks could affect the MC design, but not the MCWF
specifications that will be issued to the vendors for fabrication.
- We will be prepared to discuss the risk mitigation
plans for the windings at the FDR to the extent necessary: manufacturing
development and demonstration on the twisted racetrack and full-scale
prototype coils. We will present the minimum on this topic, but be prepared
to go deeper if called upon. We will make the point that the readiness
to proceed with MCWF fabrication is not impacted, and that the comprehensive
MC FDR is a still a few months away.
- The manufacturing development plan needs to be updated
to be sure it is adequately addressing the risks and technical issues of
concern. Most of the effort should go into developing the baseline design.
In particular, we should start fabricating chill plates ASAP. It may be
prudent to devote a portion of the effort to developing an alternate cooling
design, and perhaps demonstrate it on one side of the twisted racetrack.
Action: Jim Chrzanowski to propose an updated manufacturing
development plan addressing the issues and risks.
- At the Lehman review we will address risks in all work
packages, what is being done about them, and their status at the
time.
2. FDR
Preparations
- Drawings: Brad stated that staff has been
increased to expedite promotion of drawings to final design release
level for the FDR. It is expected that all MCWF and VVSA drawings will be
promoted to final design release at the PDR, but other drawings may still be
in process. It is thought that this will be satisfactory,
- Documents: Good progress over the weekend:
Drafts of the MCWF and VVSA design descriptions are in review. The MC and VV
System Requirements Documents are in review. MCWF and VVSA product
specifications and SOWs already issued to suppliers will be available for the
reviewers, possibly with updates. Prompt turnaround on document reviews
was requested. Documents will be posted on May 10.
3. Preparations for IPR, June 8-9
(Neilson)
- The charge, agenda, dry run plans, and speaker guidance
have been issued.
- John Schmidt will follow up on documentation other than
what is already being prepared for the FDR.
4. Procurement and Project Control
- April job status meeting is scheduled for Thursday
morning, May 6.
- Strykowsky and Neilson will meet with procurement on May
4 to address current NCSX and QPS procurement issues needing special
attention. Action: Hutch research recent metrology procurement
history with Raftopoulos.
5.
PAC-7 Meeting
The following was
discussed regarding the next PAC meeting:
- Week of July 12 appears to be the preferred window for
PAC-7. Confirm with Director’s Office and PAC chair before finalizing the
date. Decide by Tuesday COB so it can be announced at NCSX/DOE meeting
on Wednesday, May 5. Action: Mike
- Announce meeting to members and get feedback on their
attendance. Make only minimum necessary changes in membership at this time.
Action: Mike review membership and issue announcement by COB
Wednesday.
- The basic charge for PAC-7 should be:
- Advise on the research plans for the first 3 years of
operation.
- Advise on the research preparations planned between now
and first plasma.
- Update draft charge per discussion and get Rob to
approve. Action: Mike.
- Agenda ideas (not exhaustive):
- Update on NCSX project design and plans since PAC-6 and
implications for research program (Hutch)
- ARIES-CS progress and implications for research program
(Jim)
- Experimental results from W7-AS and elsewhere and
implications etc. (Mike)
- Research plan for first 3 years of operation.
- Research preparation plans from now to first
plasma.
6. Next SIT
Meeting: Monday, May 17 at 11:00 a.m. EDT. The current plan is
for no SIT meeting on May 10.
Summary by:
Hutch Neilson