Summary of NCSX System Integration Team (SIT) Meeting 
of Monday, November 8, 2004
1.    VVSA 
Procurement (M. Viola)
  - Major Tool and Machime 
  (MTM) has submitted a draft schedule. However it is inconsistent with contract 
  milestones and forecasts a delay in product delivery.  Action: Mike V. 
  to clarify expectations for MTM that they owe us a schedule which adheres to 
  the contract. Proposals to deviate from the contract will be considered if it 
  is to the project’s advantage.
 
2.   FY-05 Replanning 
and Baseline Update (Ron)
  - Ron reported the status of 
  recent replanning.  FY-05 BCWS is reported to be in the box; however 
  there is $700k growth in the EAC, not counting hardware cost risks in the TF 
  coils and field period assembly tooling. The TF cost estimate will be updated 
  at the upcoming PDR, so any growth will need to be recognized and dealt with 
  for the Lehman review. 
  
 - Follow-up 
  actions:
  
    - WBS 13: Wayne follow up 
    with Kalish to clarify WBS 130 costs and set expectations for PDR. 
    
    
 - WBS 13 & 15. 
    Cost-neutral budget reallocations among WBS 132, 133, 134, and 151 are 
    accepted. 
    
 - WBS 141:  Ron 
    explain $70.8k cost growth in MCWF. 
    
 - WBS 142-144: Cost growth 
    to ensure adequate oversight is accepted. Opportunities for cost savings in 
    the TRC, should they be needed in the future, should be identified. 
    
    
 - WBS 185:  Ron 
    follow-up to investigate possible double counting of support crew (e.g., 
    crane operator, metrology). Some savings were subsequently identified. 
    
    
 - WBS 18: Mike, come to 
    closure with Brad on possible savings in VV heating/cooling tube 
    installation. 
    
 - WBS 18 & 31: 
     Consider reducing ex-vessel magnetic diagnostic scope, to save 
    fabrication costs, installation costs and schedule. Hutch follow up with 
    Mike and Dave Johnson. 
    
 - WBS 444 & 445, 
     Wayne follow up with Raki to see if baseline coil protection and 
    instrumentation scope can be reduced. 
    
 - WBS 74, Ron follow up 
    with Erik to see if LOE machine assembly planning and oversight costs can be 
    reduced. 
    
 - WBS 73, Elimination of 
    platform identified as a cost reduction opportunity ($460k). Ron, follow up 
    to assess risks. 
    
 - WBS 53:  Hutch 
    follow up with Gary: can data acquisition and facility computing be 
    reduced?
 
   - For the Lehman review, we 
  will present
  
    - ETC from 11/1/04 for all 
    jobs, including cost variances. 
    
 - Updated risk-based 
    contingency need assessment.  Minimum total contingency is an amount 
    equal to 10% of the VVSA & MCWF contracts plus 28% on everything else. 
    
    
 - Cost risks and offsetting 
    cost-saving opportunities.
 
 
3.   Lehman 
Review, Dec. 7 (Hutch)
  - Project preparation plan 
  was briefly discussed.
 
4.   Next SIT Meeting: Monday, 
 November 15, 2004 at 11:00 a.m. EST.
Summary by:
Hutch 
Neilson