Summary of NCSX System Integration Team (SIT) Meeting
of Monday, November 8, 2004
1. VVSA
Procurement (M. Viola)
- Major Tool and Machime
(MTM) has submitted a draft schedule. However it is inconsistent with contract
milestones and forecasts a delay in product delivery. Action: Mike V.
to clarify expectations for MTM that they owe us a schedule which adheres to
the contract. Proposals to deviate from the contract will be considered if it
is to the project’s advantage.
2. FY-05 Replanning
and Baseline Update (Ron)
- Ron reported the status of
recent replanning. FY-05 BCWS is reported to be in the box; however
there is $700k growth in the EAC, not counting hardware cost risks in the TF
coils and field period assembly tooling. The TF cost estimate will be updated
at the upcoming PDR, so any growth will need to be recognized and dealt with
for the Lehman review.
- Follow-up
actions:
- WBS 13: Wayne follow up
with Kalish to clarify WBS 130 costs and set expectations for PDR.
- WBS 13 & 15.
Cost-neutral budget reallocations among WBS 132, 133, 134, and 151 are
accepted.
- WBS 141: Ron
explain $70.8k cost growth in MCWF.
- WBS 142-144: Cost growth
to ensure adequate oversight is accepted. Opportunities for cost savings in
the TRC, should they be needed in the future, should be identified.
- WBS 185: Ron
follow-up to investigate possible double counting of support crew (e.g.,
crane operator, metrology). Some savings were subsequently identified.
- WBS 18: Mike, come to
closure with Brad on possible savings in VV heating/cooling tube
installation.
- WBS 18 & 31:
Consider reducing ex-vessel magnetic diagnostic scope, to save
fabrication costs, installation costs and schedule. Hutch follow up with
Mike and Dave Johnson.
- WBS 444 & 445,
Wayne follow up with Raki to see if baseline coil protection and
instrumentation scope can be reduced.
- WBS 74, Ron follow up
with Erik to see if LOE machine assembly planning and oversight costs can be
reduced.
- WBS 73, Elimination of
platform identified as a cost reduction opportunity ($460k). Ron, follow up
to assess risks.
- WBS 53: Hutch
follow up with Gary: can data acquisition and facility computing be
reduced?
- For the Lehman review, we
will present
- ETC from 11/1/04 for all
jobs, including cost variances.
- Updated risk-based
contingency need assessment. Minimum total contingency is an amount
equal to 10% of the VVSA & MCWF contracts plus 28% on everything else.
- Cost risks and offsetting
cost-saving opportunities.
3. Lehman
Review, Dec. 7 (Hutch)
- Project preparation plan
was briefly discussed.
4. Next SIT Meeting: Monday,
November 15, 2004 at 11:00 a.m. EST.
Summary by:
Hutch
Neilson