Summary of NCSX System Integration Team (SIT) Meeting
of Monday, September 20, 2004
1. CD-3
(Hutch)
- CD-3 was approved on Sept.
16.
- Barry Sullivan, OFES, is
the new NCSX Program Manager, replacing Gene Nardella who has become the
Technology Program Manager.
- There will be a weekly NCSX
status teleconference with Pitonak, Sullivan, Lyon, and Neilson on Thursdays
at 11:30.
- The next Lehman review is
planned for Dec. 7.
2. Critical
Issues
- 12-8. VV
temperature-related risks and concerns.
- Except for the NBI ports,
the inconel-to-stainless transition occurs at the weld joint, where a
stainless flange is welded to an inconel port nozzle. The design includes
port heaters on the nozzle to keep the stresses benign during 350 C bakeout,
when the flanges are kept at 150 C. Thermal analyses have been done which
indicate that we should not have a problem at the inconel-to-stainless
transitions. Goranson is still looking at the circular conflats.
At this time, it is not believed that starting up the machine with no
active heating to the vessel body poses any risk to the machine. Loss of
power to the port heaters is a failure mode that needs to be accommodated in
any event, probably with a backup power supply.
- The heat distribution
associated with induction heating using the PF coils is being analyzed by
Art Brooks. There are no requirements on spatial uniformity of heating
for the 150 C induction heating scenario. At this time it is not
believed that there is any risk to the machine associated with heating
non-uniformity in that scenario.
- 12-6. Weld joint
R&D. Questions have been raised within the engineering team about
the baseline weld joint design, but it has a sound rationale. Small-sample
tests are beginning and the pieces will be configured so as to prototype the
baseline design. The design of the full-scale test article has been
issued for fabrication and is believed to be in the procurement process.
Larry Dudek, who is leading those tests, is on vacation this week,
but Wayne will follow up on the status in his absence and, to the extent
practicable, keep them moving. Action:
Wayne.
3. August Cost-Performance
Results (Wayne)
- Draft report was issued by
Ron for discussion. SPI and CPI are both 0.97. Some follow-up is needed
to understand the variances. Assignees are requested to respond to Ron
by Wednesday noon concerning the cause and corrective action for the cost and
schedule variances in the following jobs:
- 1403 MC Final Design-
Brad
- 1404 MCWF R&D-
Phil
- 1406 MC Winding
R&D- Wayne
- 1407 MC Winding
Facilities- Wayne
- 81 Project
Management & Control- Hutch
- 82 Project
Engineering- Wayne
4. Re-baselining
for FY-05 (Ron)
- Plan presented by Ron was
discussed and approved:
- Sept. 30, Job
manager input to Ron. Preferred format is marked-up bar charts.
- Oct. 4-8, Meetings
with job managers and management team to review
plans.
5. Next SIT Meeting: Monday,
September 27, 2004 at 11:00 a.m.
Summary by:
Hutch
Neilson