Summary of NCSX System Integration 
Team (SIT) Meeting of Monday, April 4, 2005
1. 
   Re-baselining Status
  - The current status of 
  re-baselined cost and schedule estimates were reviewed. Project schedule is 
  stretched out due to slower funding from DOE. Total cost is increased due to 
  stretchout of project core team, increased G&A/labor rates, and revised 
  estimates. Follow-up actions were assigned. 
  
 - Near-term 
  schedule:
  
    - Apr. 15.  Complete 
    Lab review of re-baseline. 
    
 - Apr. 18.  Brief OFES 
    on major cost and schedule changes. 
    
 - Apr. 18.  Start 
    posting documentation on web site. 
    
 - Apr. 20.  Dry runs 
    of Neilson and Strykowsky presentations, 1:00-5:00. 
    
 - Apr. 25.  OFES 
    review and approve new baseline.
 
 
2. 
   Critical-path Final Design Tasks 
(Brad)
  - Brad reported that an 
  efficient method for modeling the cladding and chill plates has been developed 
  and ORNL expects to begin producing drawings soon.  Status and forecast 
  FDR dates to be reported by Dave at March job status meeting later this week . 
  
  
 - Need to re-assess FY05 
  funding requirements in light of updated MC and VV design estimates done for 
  the re-baselining. Action: Brad and Ron.
 
3.  Project Control 
(Ron)
  - March job status meeting 
  will be Friday, April 8, starting at 8:30. Ron to 
  arrange.
 
4.  Next SIT Meeting: April 18 at 
11:00.
5.  Other Planning Items
  - Conferences
  
    - SOFE-05, Sept. 26-30, 
    Knoxville, TN
 
  
    
      - Phil Heitzenroeder is 
      leading in developing a list of candidate papers. He has identified about 
      19 potential NCSX papers. Although this may be a few too many, in general 
      paper submission and attendance by engineering team will be encouraged. 
      Everyone should provide feedback to Phil. 
      
 - Abstract deadline is 
      April 30.  PPPL internal deadline is April 22 to Rosemarie 
      Fuchs-Smith. 
      
 
Int’l 
    Stellarator Workshop, Oct. 3-7, Madrid.
    
      - Mike Zarnstorff is on 
      the program committee.  No deadlines have been issued. 
      
 - Anticipate an invited 
      paper on NCSX.  Engineering topics may be prominently featured 
      because of high interest in stellarator construction issues. Examples: 
      component manufacture, dimensional control, modular coil development. 
      
      
 - Update of NCSX research 
      directions and plans would be a likely paper. 
      
 - Expect maybe 3 to 
      attend from PPPL, maybe 3-4 from ORNL.
 
    - APS-DPP Meeting, Oct. 
    24-28, Denver
    
      - Deadline for review, 
      tutorial, and invited papers is May 
  18.
 
 
   - ARIES-CS
  
    - ARIES-CS Project may 
    carry a set of configurations rather than down-select to one. 
    
 - An ARIES team meeting to 
    be held at PPPL in September will include a “town meeting” of the 
    stellarator community to provide feedback on the ARIES-CS directions: 
    assumptions, configurations, plans. 
    
 - Priorities for 
    configuration studies between now and September meeting should be carefully 
    set, due to resource limitations. Meeting of Ku, Zarnstorff, Lyon, and 
    Neilson should be arranged to discuss priorities.  Action: 
    Hutch.
 
 
Summary by:
Hutch 
Neilson