From: Hutch Neilson
Sent: Thursday, April 07, 2005 2:54
PM
To: Barry Sullivan; Gregory Pitonak; Jeffrey Makiel; Sam
Barish
Cc: Michael E. Viola; Phil Heitzenroeder; Wayne T. Reiersen;
Richard J. Hawryluk; Jim Lyon; Pamela Hampton
Subject: 20050407 NCSX
procurement status
NCSX
Procurement Update of 4/07/05
1. MCWF procurement
- The C-1 casting was shipped
to Major Tool after completion of upgrades by MetalTek. Upon arrival at Major
Tool, the part was installed in the machining fixture. Positioning of the part
is being optimized for best fit of the finished part within the machining
stock.
- Fabrication and dimensional
scanning of the Type A pattern was completed by
Lawton.
- Fabrication of local
“chills” (heat sinks) for the Type C pattern is in progress, in preparation
for pouring the C-2 casting.
2. VVSA procurement
- Major Tool has begun the
panel forming process with the “first strike” on Panel #1, followed by
annealing and further pressing. Reportedly the panel formed more easily
and more closely to the desired shape than
expected.
- Die fabrication continues,
with 17 of 20 now complete.
- Fabrication of the
inspection gages and the 60-degree weld fixture
continues.
Hutch Neilson