From: Hutch Neilson
Sent: Wednesday, April 13, 2005 9:48
PM
To: Barry Sullivan; Gregory Pitonak; Jeffrey Makiel; Sam
Barish
Cc: Michael E. Viola; Phil Heitzenroeder; Wayne T. Reiersen;
Richard J. Hawryluk; Jim Lyon; Pamela Hampton
Subject: 20050413 NCSX
procurement status
We’ll have
our Thursday telecon at 11:30 as usual. I would like to discuss the status of
re-baselining, as well as the weekly procurement report. Call
877-653-7764, code 361326#. hn
NCSX Procurement Update of
4/13/05
Both of the major procurements had a very good week.
1.
MCWF procurement
- Machining of the C-1
casting is well under way at Major Tool, and reported to be progressing very
well. Delivery to PPPL is forecast for June 24, but Major Tool is
working extended shifts in an effort to improve that schedule.
- The Type A pattern passed
inspection at Lawton and was shipped to
MetalTek.
- The modifications to the
Type C pattern were completed. Latest plans call for pouring C-2 on April 15
and A-1 on April 22.
2. VVSA procurement
- Panel #1 pressing and
inspection were completed. Ready for polishing.
- Die fabrication is
complete.
- Fabrication of the
inspection gages and the 60-degree weld fixture
continues.
Hutch Neilson