Summary of NCSX System Integration
Team (SIT) Meeting of Monday, April 18, 2005
1.
Re-baselining
- New baseline parameters and
key changes will be summarized in briefing to OFES on 4/19.
- Deliverables for the 4/25
re-baselining review should be posted to the web page ASAP. Action:
Ron, Bob, Wayne, Hutch
- A CCB should be scheduled
for Friday, 4/22, to secure project and FPD approval of the baseline change
before submitting it to OFES. The baseline change must be approved by Dr.
Davies.
2. Coil Testing Plans
(Wayne)
- The menu of possibilities
is:
- Warm tests (RT):
resistance, voltage standoff to ground, hydraulic tests, possibly
turn-to-turn voltage standoff.
- Cold tests:
Cooldown to cryo temperature and repeat of warm tests.
- Power tests:
Cooldown to cryo temperature, energize to full current, and cool back
down.
- The incremental cost of
power testing is relatively high, benefits are questioned.
- Everyone agreed we should
warm test every coil, including poloidal break resistance for the modular
coils. There is a range of opinions on the extent of cold and power
testing needed.
- At this time, the project’s
position is:
- Baseline is warm testing
of all coils and cold and power testing of the first two of each of the four
types (MC-A, -B, -C, and TF).
- More extensive testing is
not precluded. If it proves to be necessary we will have to budget for
it and schedule it.
- A test program needs to
be developed and peer reviewed.
Brad
3. TF Design
Issues
- Out of plane stresses have
been recently analyzed by Kalish and Myatt for a coil current configuration
devised to serve as a proxy for flexibility requirements. Although the
model is not a detailed one, it showed regions of high out-of-plane stress in
parts of the coil that aren’t restrained vertically.
- The sense of the SIT was
that restraining the top as it is currently restrained at the bottom would
make the system up-down symmetric and probably solve the out-of-plane stress
problem. Reportedly Kalish is going in this direction already.
- Kalish is also trying to
solve a problem of high stresses in the lead region.
- Brad reported favorable TF
beam test results: the beam is strong.
- The TF FDR is scheduled for
early May.
4. Project Control
(Ron)
- Through March, CPI and SPI
are both 1.0 against the new baseline. Against the approved ECP-024 baseline,
CPI=0.97 and SPI=0.96 (preliminary). Detailed cost-performance report is not
yet available.
5. Research Prep
Quarterly Report (Mike)
- Report for second quarter
is due 4/22. Responsibility: Mike.
6. Next SIT Meeting:
May 2 at 11:00. Agenda to include kickoff of Lehman review
planning.
Summary by:
Hutch Neilson