NCSX Procurement Update of 8/31/05
1. MCWF
procurement
- Machining of the C-1
casting (MCWF#1) continues at Major Tool. They moved to the last of the four
5-axis machining set-ups last week. They are tracking close to the
schedule that was presented to us at the time of our visit about three weeks
ago. On that schedule they would complete all machining by 9/2, and ship to
PPPL 9/16. Tom Brown visited earlier this week to discuss handling of
metrology data so that PPPL is prepared to expedite evaluation of any
dimensional issues that might arise during final inspection. Phil
Heitzenroeder is visiting on 9/1 to observe
progress.
- The C-2 casting (MCWF#2)
continues making good progress progress in machining. Forecast
ship date is still October 7.
- Processing of the A-1
casting (MCWF#3) is nearly complete at MetalTek. Phil Heitzenroeder visited
MetalTek on 8/31 and reported that it looks very good and is expected to ship
to Major Tool on 8/31. MetalTek completed their dimensional re-scan of
the part using their Romer arm as part of EIO’s effort to determine the cause
of the thin-wall condition. The measurements confirmed the original 3D Scan Co
laser scanning data.
- The C-3 (MCWF#4) casting is
still in process at MetalTek but is expected to ship to Major Tool at the end
of this week.
- The C-4 (MCWF#5) and C-5
(MCWF#6) castings are in-process.
-
- The mold for the C-6
(MCWF#7) casting is complete and is expected to pour this
week.
- Fabrication and assembly of
the Type B pattern (the third and last) is proceeding ahead of schedule.
Forecast delivery date is 9/15.
- Frank Malinowski, PPPL
Procurement QA Representative, visited MetalTek last week and participated in
a meeting on QA issues.
2. VVSA procurement
- They have begun the process
of joining the first two 60-degree sectors into a 120-degree sector. This has
entailed some trial and error due to alignment challenges, and is still in
process.
- Fabrication of the third
60-degree sector is in progress.
- All panels have been
through at least first forming and anneal steps. Three of the ten types are
complete.
- Prot fabrication is
proceeding well.
- Mike Viola visited last
week and observed all ongoing activities.
Hutch Neilson