Summary of NCSX
System Integration Team (SIT) Meeting of Monday, February 14,
2005
1. New DOE Funding Guidance, Project
Schedule, and Re-baselining
- The DOE FY-06 budget
requests $15.9M for NCSX MIE and $0.700M for research prep. Because the MIE
funding guidance falls well below the baseline plan, we have been directed by
DOE to re-baseline the project. Funding guidance through FY-09 was received
for the MIE project, whereas research prep guidance was only received for
FY-06.
- Based on preliminary
planning already done, the new MIE baseline is expected to have the following
features:
- MCWF and VVSA contract
funding schedules unchanged.
- Modular coil winding
using 2 lines instead of 3, and single-shift operation.
- TF fabrication stretched
out. The issue of whether to fabricate in-house versus procure, is
re-opened. A decision will be made by March 1.
- Adequate budget
contingency, schedule contingency, and contingency profile to manage project
risks.
- First plasma delayed
approximately one year. A bottoms-up re-baselining will be necessary to
accurately update the TEC and end date.
- A schedule for developing a
new baseline was issued. The goal is to complete the re-baselining by
the end of April. The first step will be a call for WBS managers to update
their ETCs and contingency risk assessment. Action: Ron issue
guidance and ETC update schedule.
- Updated labor rates through
FY-09 are needed to support the re-baselining. Action: Jim for ORNL, Ron
for PPPL.
- It was decided that we do
not need an all-hands meeting to discuss the budget. A short comment will be
made at Wednesday’s WBS 1 meeting. Action:
Hutch
2. Research Planning
Activities
- Report on HSX & CTH
contributions to NCSX research preparation. Draft was issued 2/13. Goal is to
submit to Sam Barish by Feb. 18. Mike
- Stellarator Program White
Paper. Drafts of Introductory and Physics Issues chapters were issued by
Jim. Comments are requested. According to the schedule, drafts of the
NCSX and other program component chapters are due March 1. Jim,
Hutch, Mike.
- BPM talks. Jim will
cover NCSX programatic aspects and research prep budgets in his program talk.
Hutch will cover NCSX MIE status and budget requirements. A question is how to
handle HSX and CTH budgets in the program talk. Jim will follow up with Sam
Barish.
- Research prep budgets.
Action: Hutch follow-up with Dave Hill and Sam to get the FY-06 research
prep budget distribution aligned with the project’s plans.
- Fusion Science &
Technology special issue. We continue to believe there is value in publishing
the NCSX physics design chapters in a special issue of F.S.&T., and it is
our intention to do so. However, due to the continuous demands of higher
priority tasks, we are unable to commit to a schedule for submitting the
chapters that are outstanding. We will inform the editor, Nermin Uckan, and
the other chapter authors of this. In the future, once we have a
complete set of chapters ready to go forward for publications, we will contact
the editor and re-plan. Action: Hutch discuss with editor.
- Program Advisory Committee.
A teleconference with the PAC will be arranged to discuss the new NCSX
funding plan and its implications for the program. Dave Anderson, PAC
chair, was contacted and agreed. Tentative date is March 3.
Action: Hutch arrange meeting.
3. Next SIT
Meeting: t.b.a.
Summary by:
Hutch
Neilson