NCSX Procurement Update of 7/06/05
1.
MCWF procurement
- Machining of the C-1
casting (MCWF#1) continues at Major Tool. They report being 90% complete on
the roughing and semifinal machining, which corresponds to the 3-axis
operations which were forecast to be completed by July 8 in the detailed
schedule submitted on 6/17. The have not flipped the part to the second side
yet because they found they could do more on the initial setup than had been
anticipated. As of July 1, they reported being 2-3 days behind the 6/17
schedule.
- The 5-axis experimentation
using the prototype continues to be beneficial. Through trial and error they
have found the best setup for fixturing the casting in the mounting plate
during 5-axis machining, increasing the clearance for the 5-axis head. They
estimate that this effort avoided 2 days of schedule growth in the
5-axis machining of the C-1. They also proved out a method for machining
the groove.
- The C-2 casting (MCWF#2)
was setup in the machining fixture at Major Tool and machining operations
began on July 1.
- Radiographic inspection of
the A-1 (MCWF#3) casting indicated very good casting quality with no
regions of “shrink,” or inadequate metal supply. The subcontractor who
performed the laser scanning dimensional check is scheduled to return to
MetalTek this week to repeat the measurements in areas that did not scan
properly.
- The C-3 (MCWF#4) casting
was shipped to Milwaukee for radiographic testing this
week.
- Mold setup for the C-4
(MCWF#5) casting is at least 40% complete and due to pour by the end of this
week.
- Fabrication and assembly of
the Type B pattern (the third and last)
continues.
2. VVSA procurement
- The first 60-degree shell
sector (consisting of 10 panels) is being fabricated by first welding panels
together in subgroups of 2 or 3, then welding the subgroups together.
Two 3-panel subgroups and one 2-panel subgroup have been welded. Another
2-panel subgroup will be welded over the
weekend.
- The first 120-degree
fixture (of 3) is complete. The remaining two are being
welded.
- Of the production panels,
16 have been through first forming, of which 6 have been through final
forming.
Hutch
Neilson