NCSX Procurement
Update of 6/29/05
A project delegation visited Major Tool and Machine at
their Indianapolis facility on June 27-28, along with representatives from EIO,
MetalTek, and DCMA. We developed plans to support the upcoming inspection
and release of the MCWF#1, observed the MCWF and VVSA fabrication in progress,
and discussed schedule issues.
1. MCWF procurement
- Machining of the C-1
casting (MCWF#1) continues at Major Tool. They are still in 3-axis operations
and expect to flip the part to the second side last night or today. The
prototype winding form is on the 5-axis machine, where it is being used to
develop the 5-axis machining program before the C-1 reaches the 5-axis
machine.
- EIO and Major Tool continue
to forecast that the C-1 will ship to PPPL on July 30, although the three-axis
operations are taking longer than expected. Appropriate actions are
being taken to maintain schedule for the upcoming 5-axis operations and final
inspection and release. Nonetheless, our assessment of the schedule is the
same as we reported to OFES on June 24, namely that it is likely to slip
further due to the continuing need for machining
development.
- The foundry portion of the
C-1 documentation package was formally submitted to PPPL. At the Major Tool
meeting, plans were developed for PPPL engineering and QA staff to support the
final inspection and test activities and perform concurrent review of the
final set of documents at Major Tool in order to avoid unnecessary delays in
releasing the part for shipment.
- The C-2 casting (MCWF#2)
was shipped from MetalTek and arrived at Major Tool on June
28.
- The A-1 (MCWF#3) casting
has returned from radiographic testing and the films are currently under
review. There were issues with the laser scanning dimensional check that was
done last week so the subcontractor will be brought back in to repeat some of
the measurements.
- The C-3 (MCWF#4) casting
has been heat treated and visually inspected. It appears to be of very good
quality, reportedly the best to date. It may be the next to ship to Major
Tool.
- Some components of the Type
B pattern (the third and last) have been fabricated and the assembly process
has started.
2. VVSA procurement
- Both 60-degree fixtures are
complete and are being used for sector
fabrication.
- The first ten
panels, the so-called development panels, are complete. All the
production panels have now completed the “skin” removal process. Thirteen of
these have been through the first pressing operation and are in
process.
- Fabrication of
the first 60-degree sector has started. Five panels have been mounted on the
fixtures and seam welding is in
progress.
Hutch
Neilson