NCSX Procurement Update of
3/30/05
1. MCWF procurement
- Last week, the C1 casting
was found to require re-work of a few of the weld repairs. Despite a MetalTek
plant shutdown over the holiday weekend, a crew came in to finish the C1.
Liquid penetrant inspection this week confirmed that the repairs were
successful, and preparations were under way earlier today to ship the part to
Major Tool for machining.
- The final problem areas in
the solidification model for the C Coil have been resolved. The required Type
C pattern modifications are relatively minor and will be carried out by
MetalTek.
2. VVSA procurement
- Major Tool continues to
machine, deburr, and inspect the dies, and are fabricating the inspection
gages.
- Fabrication of the
60-degree weld fixture has started.
Hutch Neilson