Summary of NCSX System Integration
Team (SIT) Meeting of Monday, May 2, 2005
1.
Modular Coil Winding Plans
(Wayne)
- A detailed checklist has
been prepared to track preparations for starting to wind the modular coils.
Schedule, issues, and deliverables are identified. The checklist will be
maintained and tracked at weekly meetings. An up-to-date copy is posted at http://ncsx.pppl.gov/NCSX_Engineering/Management/Checklists.xls.
- A similar plan for the TF
coil design closeout is posted in the same
place.
2. Project Control (Hutch,
Ron)
- The re-baseline review on
April 25 went well. However, an internal DOE ESAAB must be convened to
approve the baseline change, and the schedule for completing that process is
currently unclear.
- We will align our near-term
work plans with the new stretched-out schedule, and adjust the near-term
performance measurement baseline (PMB) accordingly. An ECP is being prepared
to make some zero-net-cost budget adjustments in the PMB. A CCB meeting
is scheduled for Wednesday, May 4, to consider that ECP (ECP-031). The
intent is to measure April performance against the ECP-031 baseline.
- The April job status
meeting is planned for Friday, May 6 at 8:30
a.m.
3. Summer Schedule
- A vacation schedule will be
compiled.
4. Next SIT Meeting: May 16 at 11:00.
Summary by:
Hutch
Neilson