Summary of NCSX
System Integration Team (SIT) Meeting of Monday, November 21,
2005
1. Management
- Hazard Awareness Training
was attended by 9 ORNL/UT participants on Nov. 16. Others interested in
taking the course should contact Hutch.
- FY-06 funding update for
NCSX. We expect $17.27M, $15.57M to PPPL, $1.70M to ORNL. Of these
totals, 3% may be held back by site offices or lab against a possible
recission.
- Next Lehman Review will be
May 9-10.
- The project is on the
Office of Science watch list, so that they can monitor progress in MCWF
deliveries and MC winding. Pitonak or Makiel will brief SC on Dec. 14,
and may contact us for input. Wayne
- October cost-performance
report was reviewed. Apparent variances in 1403, Modular Coil Final
Design, and 1416, Modular Coil Type A&B Final Design may be partly due to
mis-charging of work, including coil interface hardware design and MCWF Title
III design, to these jobs. Action: Brad determine how real the
1403 and 1416 variances are.
2.
Risks
- MC parts availability.
(Larry)
- Chill plates: drawings
were issued last week. A requisition was approved and an RFP for 6 full sets
is expected to be issued this week.
- Cladding: an order has
been placed. Delivery is expected to meet schedule needs, but price exceeds
amount budgeted by a factor of ~2.
- Tracking of needed
drawings and parts orders. Larry will review the BoM generated by Dave
Williamson for completeness of the drawings and iterate with Dave as
necessary. Action: Larry.
- MC design cost &
schedule risks. MCWF Title III may have significantly impacted the work during
the past month. However, Type A cladding drawings are 75% complete.
Williamson commented in an afternoon meeting that there have been
improvements in the process for generating cladding and chill plate drawings.
Rushinski of PPPL will be re-assigned to Type A&B cladding & chill
plate work to speed up drawing production.
- VV design & procurement
risks: Requisition issued for cryostat interface flange (“horse collar”).
Assembly drawings for H&C manifolds and heater tapes are still being
developed. These are needed for procurement.
- H&C tubes: a readily
available catalog item will be used, so procurement lead time is no longer
considered to be a risk. A prototype has been ordered for attachment heat
transfer tests to resolve the performance issues.
- Procurement process.
Typically taking 90 days from requisition to delivery for parts procurements.
We are not sure how the approval requirements are decided. Action: Ron
look into it.
- Tracking of needed drawings
and parts orders for VV. The “-049” drawing, under development,
identifies most of the parts needed for Station 1. The “-004” drawing
shows the heater tapes. Currently these play the role of a BoM.
- MC quality conformance
issues. (Wayne)
- Cladding conformance
issues: Procedure being modified to include an dimensional acceptance
criteria and QC inspection. Metrology scan will be performed on the
completed cladding surface instead of on the ground wrap. Training in
cladding installation is being conducted to ensure uniformity of key process
steps, e.g. bending, glue application.
- Twisted Racetrack Coil:
Art Brooks is responsible for getting the sectioned coil measured and
documented. Kevin Freudenberg completed analysis comparing temperature
response to analytical results. Strain gauge data is still being
studied; masurements and predictions have not been reconciled. Action:
Brad.
- A meeting will be scheduled
with Wayne and Ron next week to finalize FY06 work schedule.
Hutch
3. Next SIT Meeting: Dec.
5
Summary by:
Hutch Neilson