Due to the Thanksgiving holiday there
will be no telecon this week. Contact me if there are any questions.
hn
NCSX Procurement Update of 11/22/05
1. MCWF
procurement
Machining operations:
- The C-2 casting is in its
final machining operation on the 5-axis machine. The project’s expectation is
that it will ship around Dec. 10.
- The C-3 casting continues
making good progress through 3-axis machining operations. They are currently
roughing the poloidal break.
- The C-4 is in rough
machining on the Lucas machine. A total of 3 castings, C-2, C-3, and
C-4, are in machining operations on three different
machines.
- The A-1 casting is at Major
Tool.
Foundry operations:
- The C-5 has completed
foundry operations. Final documentation review is in progress prior to release
for shipment to Major Tool.
- The A-2 is undergoing weld
upgrades.
- The A-3 is in its first
radiographic testing.
- The B-1 casting was shaken
out of its mold and the gating system cut off.
- The C pattern has been set
up in preparation for re-pouring the C-6
casting.
2. VVSA procurement
- Welding of ports into the
first 120-degree segment continues.
- The second 120-degree
segment has completed radiographic testing and is in the queue for machining
the port openings.
- Fabrication of the large
ports is progressing.
- Fabrication of the first
spacer is almost complete.
Hutch
Neilson