Summary of NCSX
System Integration Team (SIT) Meeting of Monday, October 10,
2005
(concluded on Oct. 11, 2005)
1.
FY-06 Planning and Budget Strategy
- All necessary estimate
updates have been submitted and reviewed except WBS 17.
- We converged on the project
plan to present at the Lehman review:
- Request contingency to
cover FY-05 variances where the risks are retired. Might carry some
variances for another few weeks and pick them up in subsequent ECPs, but all
variances will be visible.
- Request contingency to
cover the estimate in most of the FY-06 jobs that have increases, including
increases in MC design, VV design, coil interface hardware, and management.
- In the case of MC and TF
winding, we recognize the increased estimates as having a sound basis, but
request contingency for only the first 3 MC and first 2 TF coils at this
time. We will learn a great deal about production costs after the first few
coils and will re-evaluate budget needs after that.
- We will maintain a
management focus on process improvement throughout these production
activities. This is the new focus of our VE activities.
- Offset contingency
requests with some value improvements and work reductions, including some
changes in the technical baseline which we have been analyzing recently:
simpler e-beam mapping equipment, simpler trim coils, substitute PF1a for
the central solenoid.
- The contingency will wind
up around 20%, plus or minus.
- Risks recently recognized
but still being worked and not yet quantified: TF wedge casting
price, poloidal break bolts, growth in FY-07 FPA tasks.
2. Lehman Review
Preparation
- Plans have been updated
based on DOE guidance and changed project situation with the arrival of the C1
MCWF. Review is expected to emphasize credibility of realism of project cost
and schedule estimates.
- Revised agenda and speaker
guidance was issued.
- Documentation requirements
wee reviewed. To be posted next week.
- Dry runs are scheduled for
Oct. 20-21. Presentations will be posted the week of Oct. 24.
- Updated planning package
was issued to SIT and all speakers.
3. Next SIT Meeting:
t.b.a.
Summary by:
Hutch
Neilson