Summary of NCSX
System Integration Team (SIT) Meeting of Monday, September 12,
2005
1. Housekeeping and
Safety
- Housekeeping tours of NCSX
manufacturing and test areas highlighted need for a master plan for space
utilization in the TFTR test cell. It needs to be time-phased and needs to
address storage as well as operational needs. Responsibility: Dudek
- Radiation hazard control in
the TFTR test cell: procedures worked out with HP for controlling access to
the test cell, movement of materials in and out, etc. have worked well over
the past year. We need to work at maintaining this same culture as the level
of activity increases and new people get involved in the activities there.
Responsibility: Neilson.
2.
Management Issues
- Lehman Review, Nov. 2-3.
Review committee will be: Steve Meador (SC), chair; and Dave Anderson
(U.Wisc.), Ron Lutha (DOE-Fermi), Joe Minervini (MIT), and Kin Chao (SC).
- FY-06 Work planning.
Outstanding estimates need to be submitted. We will start holding
management reviews of estimates and plans. Action: Ron schedule and
coordinate reviews.
3. Targeted Schedule
Risks
- Job 1414, Twisted Racetrack
Coil testing. Good progress last week, summarized in separate e-mail reports
from Gettelfinger and Schneider. Reached 20 kA, 1.5-second pulses. Progress
was halted by multiple issues including leaky LN plumbing in the coil
cryostat, cryo system problems, and power supply problems. In response, we
need to:
- Make necessary repairs,
resume testing, and try to complete the program as planned. Wayne
- Review the data already
acquired to determine its usefulness and carefully set priorities for
additional data needs, in case the program cannot be completed as planned.
Wayne and Brad.
- Job 1203, VV design.
We will go ahead with the FDR scheduled for this Friday, Sept. 16, but
it will be planned as one part of a multi-part FDR. Action: Wayne /
Brad develop charge for this week’s FDR and a plan for completing the VV
final design.
- Job 1411, MCWF Fabrication.
Major Tool has slipped a few days relative to their most recent schedule
forecast, due to difficulties in finishing the poloidal break. They forecast
ship to PPPL Sept. 23; we expect delivery in September. We will maintain daily
contact on schedule status and plans for final inspection and test.
Responsibility: Phil.
4. Next SIT Meeting:
Sept. 19.
5. Research Management Issues
- ARIES-CS Meeting Sept.
15-16
- Mike will post call-in
instructions for stellarator community off-site participants.
- We need to help the ARIES
team get clear feedback on the CS assumptions they are using and their plans
for completing the study. Hutch will moderate the discussion.
Mike should prepare slide(s) with feedback and recommendations
to put up for discussion.
- APS Satellite Meeting on
Research Opportunities in Stellarators.
- Jim has scheduled it for
Wednesday, Oct. 26, at 2:00-3:30. PPPL will pay for meeting services.
Pamela will work with the conference services people. Will request
projector, screen, and microphone from the hotel. We (Jim) will
provide our own computer.
- We agreed the agenda
should: emphasize research opportunities that would interest the
target audience, combine some of the talks, be planned for 1 hour, be
extended to 1.5 hours if warranted by the level of discussion/interest.
- Tentative
agenda:
Program
overview, J. Lyon
HSX & CTH, D. Anderson
NCSX, M.
Zarnstorff
QPS, J.
Harris
- Next steps (Jim):
update agenda (with times), coordinate plans with speakers and provide
guidance, design a poster to advertise the meeting, coordinate the talks to
ensure coherence (rehearsals).
- FY-05 3Q Progress Report,
and FY-06 priorities and work plans. Most of FY-05 plans have been
accomplished; some boundary tasks will be completed early in FY-06.
Meetings are planned to develop FY-06 plans. Magnetics and
Boundary are the key areas. Priorities will have to be carefully set,
given the relatively small budget for research
prep.
Summary by:
Hutch
Neilson