Summary of NCSX
System Integration Team (SIT) Meeting of Monday, September 19,
2005
1. Management and Project
Control
- FY-06 estimate reviews for
WBS 12, 13, 18, 8 were scheduled for this week. WBS 15 & 17 will be after
SOFE.
- Estimate growth must be
managed in a way that does not involve steep contingency draw-downs. Plan is
to draw contingency as it’s used, keeping it at about 25% or higher.
Candidate savings to offset estimate growth will be identified.
- An issue is how to handle
coil interface hardware, a ~$1M item previously overlooked and therefore not
currently budgeted. Responsibility:
Hutch
2. Targeted Schedule
Risks
- Job 1414, Twisted Racetrack
Coil testing. Hope to finish high-power testing soon.
- Job 1403, Modular coil
design and drawings. Designer staffing will be augmented to provide more
schedule contingency. Need to decide between using ORNL or PPPL
resources early this week. Action: Brad.
- Job 1411, MCWF Fabrication.
Major Tool still forecasts shipping C1 to PPPL Sept. 23; we expect
delivery in September. We are maintaining daily contact on schedule status and
plans for final inspection and test. Responsibility: Phil.
- Job 3101, Magnetic loops
physics requirements (Mike Z.)
- Flux loops. Expect to
require ~200-220 loops. Requirements will be delivered by Sept. 23. Physics
should not delay delivery of physics requirements (number and geometry) to
tackle engineering tasks such as rounding of the corners. Physics
should interface with Mike Cole.
- Diamagnetic loops.
Ex-vessel loops are likely needed (potentially new scope).
Configuration needs to be determined. Is it possible to use modular coils’
co-wound loops? Lower priority than flux loops, since the latter are now
schedule-critical.
- Job 1203, VV design. Last
week’s FDR (Part I) showed design is going in the right direction but
incomplete in significant ways. Further discussion by the SIT came to the
following conclusions.
- Heating & cooling
tubes: Adopt flexible tubes as the baseline because we had no bids on the
hard tubes and the flex tubes are expected to be significantly cheaper to
procure and install. The performance may be less, and needs to be quantified
ASAP via testing and/or analysis. The support pads may need to be closer
together to compensate for lower performance.
- Insulation material:
Adopt nanogel as the baseline, since we only require 150 C and nanogel is
good to 250 C. Replace it with something else (t.b.d.) later when we upgrade
to 350 C..
- Procurements: A bill of
materials is needed to package the procurements and provide visibility of
all hardware. Action: Ron take the lead in drafting a bill of
materials for WBS 12.
- Interfaces: a meeting
will be held of all WBS managers having interfaces with WBS 12 to work
interface issues. Responsibility: Wayne.
- Priorities for
procurement and implementation: the heating and cooling tubes have
priority because they are needed first.
- Completing the Title II
design. We need to wrap up the loose ends and determine what is needed in
the way of assembly drawings and other documentation. We need to decide how
to subdivide the remaining reviews. Responsibility:
Brad.
- WBS 18, Field Period
Assembly. Station 1 (VV Prep Station) FDR was successful. Need to decide
how many we need. Depends on budget and schedule
considerations.
4. Next SIT Meeting: Oct.
10.
Summary by:
Hutch
Neilson