Summary of NCSX On-Site Fabrication Meeting of 
Tuesday, August 8, 2006
1.  Cost Trends and 
Issues
  - We reviewed the latest cost 
  tracking charts (8/3/06) and made the following 
observations:
  
    - Significant uptick in 
     A1 costs (through stud installation) compared to the recent C’s. 
    
    
 - Noticeable upward trend 
    in recent Type C costs. 
    
 - Large jump in shop & 
    “other” tech. support hours (other than the winding crew) in July (400 hrs.) 
    relative to May and June (~150 hours) and budgeted amounts (~120 hrs.) 
    
    
 - Unbudgeted winding crew 
    tasks continue. For example,Type C cladding and chill plate re-work, C1 
    repairs and test prep.
 
   - We discussed various 
  hypotheses to explain the adverse cost trends.
  
    - “Learning curve” penalty 
    on A1 (certainly a factor). 
    
 - Inefficiencies and 
    activity stretchout due to sub-critical staffing on A1?  (We have not 
    made much progress for the amount of time we have been working on it. 
    Staffing has been off and on.) 
    
 - Inefficiencies on the 
    recent C’s due to new and inexperienced staff?  (If so, should see 
    improvements as new staff gain experience.) 
    
 - Inefficiencies due to 
    “logjams” in the facility?  (If so, should see improvements once the 
    new winding fixture is installed.)
 
   - Follow up 
  actions
  
    - Closely monitor 
    operations to determine whether the above hypotheses are valid, and if 
    corrective measures are needed.  Larry, Mike W. 
    
 - Move ahead with the new 
    winding fixture ASAP. Larry, Ron. 
    
 - We are not ready for 
    additional technician hires at this time. Re-visit in September. 
     Mike W. 
    
 - Determine the cause of 
    unbudgeted work trends, and the jump in shot and other tech. hours. 
    Ron
 
 
2.  Schedule Trends and 
Issues
  - We are falling further 
  behind, in spite of recent staff increases.  C4 and C5 are about 13 days 
  behind, A1 about 8 days behind. Why? 
  
 - When will we go to two 
  shifts on Station 1b?  Larry
 
3.  Next 
Meeting:  August 15 at 
9:00
Hutch