From: Hutch Neilson
Sent: Wednesday, August 09, 2006 10:18 PM
To: Jeffrey Makiel; Barry Sullivan; Ronald L. Strykowsky; Jim Lyon
Cc: James H. Chrzanowski; Michael E. Viola; Pamela Hampton; Phil Heitzenroeder; Wayne T. Reiersen; Richard J. Hawryluk; Sam Barish; Robert J. Goldston; Gene Nardella; Bradley E. Nelson; Michael R. Kalish; Gregory Pitonak
Subject: 20060809 NCSX weekly update
There will be no telecon on Thursday due to the all-day meeting with EIO. How about Friday at 9:30? Hutch


NCSX Weekly Update of 08/09/06

1. Modular Coil fabrication (PPPL)

MC Fabrication summary status:
3 coils through VPI to date  
3 coils in winding form prep and winding operations
2 in the queue

C-1 Coil

C-2 Coil

C-3 Coil

C-4 Coil

C-5 Coil

A-1 Coil

A-2 Coil

A-3 Coil

Summary comment: As expected, critical-path winding operations continue to experience schedule slippages throughout the summer months, and are currently 8-14 working days behind.  The two main causes, and how they are being addressed, are as follows:
  1. Understaffing: four new technicians have been hired and are joining the winding crew as they complete new-employee training. It will bring the total crew size to 18 technicians. Vacations also are having an impact which will continue at some level through September, although we believe the peak is behind us for this year.
  2. Facility backups: an additional winding station will be procured. When installed (by Dec. 1) this will provide greater operational flexibility and should improve flow of coils through the facility.


2. MCWF procurement (Energy Industries of Ohio)

MCWF summary status:
All 18 castings have completed foundry operations
5 in active machining operations
5 in the machining queue
8 shipped to PPPL

Machining operations (Major Tool and Machine):

B-1

B-2

A-4

B-3 and B-4

The expected delivery sequence for the next few coils is A-3, B-1, B-2, A-4. All are on or ahead of schedule.

A-5, A-6, B-5, B-6, and C-6

EIO and Major Tool personnel will visit PPPL for a MCWF Contract Status Meeting on August 10.


3. VVSA procurement (Major Tool and Machine)



4. TF Assemblies procurement (Everson Tesla, Incorporated)



Hutch Neilson