NCSX Weekly
Update of 08/23/06
1. Modular Coil fabrication
(PPPL)
MC Fabrication summary status:
3 coils through VPI
to date
1 in VPI operations
2 coils in winding form prep and winding
operations
2 in the queue
C-2 Coil
- In queue for post-VPI
cleanup.
C-3 Coil
- In post-VPI cleanup.
Permanent clamps are being installed.
C-4
Coil
- Successfully VPI’d this
week. Currently in the cure cycle as of this
writing.
C-5 Coil
- Winding pack dimensional
adjustments and final pack measurements complete.
- VPI prep completion
milestone is August 16. Currently 18 working days behind
schedule.
A-1 Coil
- Initial ground wrap
installation complete. Placement of lacing strips in progress.
- VPI prep completion
milestone is October 2. Currently 9 working days behind
schedule.
A-2 Coil
- In the queue for winding
operations.
- VPI prep completion
milestone is November 10. Currently on
schedule.
A-3 Coil
- In the queue for winding
operations.
2. MCWF procurement (Energy Industries of
Ohio)
MCWF summary status:
All 18 castings
have completed foundry operations
5 in active machining operations
5 in
the machining queue
8 shipped to PPPL
Machining operations (Major Tool
and Machine):
B-1
- The B-1 spent most of last
week in 3-axis operations in the Mitsu-30. Programming changes were needed to
deal with some difficult, but localized problem areas on the winding form.
After several days’ delay, it moved to the U-5 on Saturday 8/19, whereupon
5-axis machining operations immediately began. These problems and the
associated delays are normal for the first casting of a Type. Additional
time was needed to develop solutions that are expected to save time on the
remaining Type B’s.
- Some overstocked areas on
the B-1 as-cast surfaces were identified. It will likely require machining by
MTM to remove the excess material. Currently under evaluation.
- A mid-September B-1
delivery is still expected. The project’s delivery milestone is September
20.
B-2
- The B-2 is in 3-axis
machining operations on the Mitsu-40.
- The project’s delivery
milestone is November 29 for B2.
A-4
- The A-4 has completed Lucas
40T operations and is in the queue for the Mitsu-40.
- The project’s delivery
milestone is October 24 for A-4.
B-3, B-4, and
B-5
- The B-3, B-4, are rotating
through rough machining operations on the Lucas 40T.
- The project’s delivery
milestone is January 11 for B-3.
- The project’s delivery
milestone is February 14 for B-4.
- The project’s delivery
milestone is March 20 for B-5.
The expected delivery sequence for the next few
coils is B-1, B-2, A-4, B-3, B-4. All are on or ahead of
schedule.
A-5, A-6, B-6, and C-6
- The A-5, A-6, B-5, B-6, and
C-6 are in the queue for machining.
3. VVSA procurement (Major
Tool and Machine)
- VVSA #3: The ports are
being temporarily re-attached for final alignment. Still on track for
September 15 delivery.
4. TF Assemblies procurement (Everson Tesla,
Incorporated)
- Clean room construction
progressing.
- Winding fixture fabrication
is progressing. Completion expected by 9/15.
- Fabrication of the braze
coil for the Robitron is progressing. Expected to ship
8/28.
Hutch Neilson