Greg, Jeff, and Barry,
We’ll have our Thursday
telecon at 9:30. Call 877-653-7764, code 361326#.
Hutch
NCSX Weekly
Update of 01/04/06
1. Modular Coil fabrication
(PPPL)
C-1 Coil
- The detailed dimensional
scan of the winding pack continues.
- We expect to complete the
C1 coil by 2/28/06, or 29 days ahead of schedule for the Level II milestone
scheduled for March.
C-2 Coil
- The dimensional scan of the
winding surface was completing
- Winding clamp support studs
are being installed.
- We expect to complete the
C2 coil by 4/17/06.
2. MCWF procurement (Energy Industries of
Ohio)
MCWF summary status:
11 poured to
date
4 in foundry operations
5 in machining operations
2
delivered.
Machining operations (Major Tool and
Machine):
C-3
- The C-3 is in 5-axis
operations on the U5. Repair of the tool gouge that occurred before the
holidays was completed but delayed the schedule. Major Tool now forecasts
delivery of C-3 on 2/10/06, but allowing for normal delays we expect it around
the end of February.
C-4
- The poloidal break was cut
and the C-4 is now being machined on the Mitsu-40. Major Tool forecasts
delivery of C-4 on 3/10/06. Our assessment is that it will be in
April.
C-5
- The C-5 is in the queue for
the Mitsu-40.
A-1
- Rough machining of the A-1
on the Lucas-40T is expected to start in the near
future.
A-2
- The A-2 completed foundry
operations over the holidays and was shipped to Major
Tool.
- An NCSX delegation from
PPPL and ORNL is at Major Tool this week to discuss possible technical changes
that could improve the machining
schedule.
Foundry operations (MetalTek International):
A-3
- Weld repairs were completed
and the A-3 will be shipped to MQS for radiographic
testing.
B-1
- The B-1 is at MQS for
radiographic inspection.
C-6
- The C-6 is at MQS for
initial radiographic inspection.
A-4
Casting
- The A-4 casting is
ready for heat treat.
A-5 Casting
- Setup of the A pattern is
in progress in preparation for pouring the A-5 in
mid-January.
3. VVSA procurement (Major Tool and
Machine)
- The end flanges are being
tacked onto the first 120-deg segment in preparation for the final
weld.
- The second 120-degree
segment is on the DSI milling machine, and the large port openings have been
cut.
- Fabrication of the fifth
and sixth 60-degree half-segments continues.
- Fabrication of the first
spacer is completed and the second is in
progress.
- All neutral beam ports are
completed, and fabrication of the remaining large ports for segments 2 and 3
continues.
- Major Tool’s delivery for
the 3 VVSA segments: 3/27/06, 5/15/06, and 6/16/06. The final sector
delivery forecast date is 2.5 months ahead of schedule for the Level II
milestone scheduled for September.
Hutch Neilson