From: Hutch Neilson
Sent: Monday, July 10, 2006 10:54
PM
To: Bradley E. Nelson; Jim Lyon; Lawrence E. Dudek; Mike Williams;
Michael C. Zarnstorff; Phil Heitzenroeder; Wayne T. Reiersen; Ronald L.
Strykowsky; Mike Cole
Subject: Summary of NCSX SIT Meeting of
7/10/06
Summary of NCSX
System Integration Team (SIT) Meeting of Monday, July 10,
2006
1. Safety items: follow-up on issues from
recent ISM review
- Hazard controls in JHA and
procedures.
- There is a proposal to
incorporate the JHAs into our manufacturing procedures as a means of
controlling the JHAs and keeping the JHAs and procedures consistent. This
would keep them in sync, but a concern was expressed that it would make it
more cumbersome to change the JHA. The flexibility to change the JHA in the
field in response to changing needs is considered vital. It was decided to
hold off on the proposal to incorporate the JHA into the procedure, and give
it further consideration.
- The Lab is re-visiting
the JHA procedure.
- NCSX procedures: VPI
procedure has been revised. New autoclave access procedure has been written.
The autoclave operations procedure was to have been revised to include
references to the access procedure and improved safety notes. What is the
status/plan? Larry
- Formal tracking of ISM
review responses. Wayne will identify items for which NCSX is
responsible and propose disposition. Coordinate with Jerry Levine, et al., who
are preparing the Lab response.
2. Management
Items
- Status of pending work
scope issues, discussed in draft memo of 6/29/06.
- MC flux loops: cancelled.
Use to help offset WBS 3 cost variances.
- Magnetic Alignment will
not be incorporated into the MIE project plans. Requests for
research-supported measurements of inductances at various sub-assembly
stages will be accommodated to the extent possible without impacting the
schedule.
- Trim coils on the MC
shell: it is argued that the MC shell may be the only practical location for
trim coils, but there are no plans for such coils. A side discussion is
planned to better understand the requirements and options. Action:
Hutch
- Additional cold testing:
Wayne is leading analysis effort to support decision by July
31.
- Third winding fixture:
Larry is obtaining the cost estimates, and Wayne is performing
process simulations needed to support a decision by July 31. Some of
the fixture drawings need to be updated. Larry will check with
E. Perry regarding installation costs.
- Cost performance
improvement
- We are launching an
initiative to improve cost performance in the remainder of FY06.
- Monthly cost variances
have been in the –$300k to –$400k range and monthly CPI has been 0.7-0.8.
Proposed goal is to improve monthly CV to >–$150k and CPI to
>0.90.
- A plan was requested by
the Director’s Office. It is needed to improve DOE confidence that the
project can be completed within the present baseline. A plan has been
documented by Ron and circulated to the SIT. Action: SIT review and
comment on the cost performance improvement
plan.
3. Risks
- C1
repair:
- Mike W. reported that the
lead block cover was removed and the resistance to ground (measured with a
9V DVM) immediately increased to a high value. Subsequent meggar check
at 7.5 kV measured 15 GOhms. These findings confirm the previously suspected
cause and location of the fault.
- A peer review of the
proposed repair procedure will be conducted on Tuesday.
- A decision needs to be
made on whether to also modify C2, which passed a 7.5 kV meggar test. The
decision will await repair of C1 and Chrzanowski’s return from
vacation.
- Analysis of C1 test
results
- Displacement monitor
results compare reasonably well with analysis, under consistent support
assumptions.
- Strain gauge results are
still not well understood.
- Cooldown results suggest
issues with the cryogenic system including the cryostat, that may need to be
addressed for the system to be installed on the machine. Some testing and
development may be desired.
- Goal is to complete the
analysis and decide on future testing by July 31. Responsibility:
Wayne.
4. Next SIT Meeting: July
24
Summary by:
Hutch
Neilson