From: Hutch Neilson
Sent: Tuesday, June 20, 2006 12:00
AM
To: Hutch Neilson; Bradley E. Nelson; Jim Lyon; Lawrence E. Dudek;
Mike Williams; Michael C. Zarnstorff; Phil Heitzenroeder; Wayne T. Reiersen;
Ronald L. Strykowsky; Mike Cole
Subject: Summary of NCSX SIT Meeting
of 6/19/06
Attachments: SC Recommendations Log.doc
Summary of NCSX System Integration
Team (SIT) Meeting of Monday, June 19, 2006
1.
Safety items
- Need to follow up on
recommendations of recent ACC review of FPA stage 1. Tour safety: Hutch.
Lighting and trip hazards: Larry.
- Results of ISM
Re-verification Review, June 12-16. Generally positive outcome,
complimentary of NCSX. Issues for us were identified in the areas of
confined space permits (paperwork issues and control of energy sources) and
JHAs (PPE requirements spelled out? Change control?). Immediate
actions (Larry following up):
- Crew meetings this week
to review permit use and PPE requirements.
- NCSX permits (including
but not limited to confined space) being reviewed by A. Langella.
- Is there a weakness in
LOTO procedures that allows an energy source to be restored while a
confined-space permit is still open?
- JHA change control still
needs to be addressed.
2. Management
Items
- Recent Lehman
review.
- Please attached review
recommendations log. Still some outstanding questions.
- ECP-045 was approved,
with some changes from the plan presented at the
review.
- May cost performance report
had incremental CPI>1 due to a change in budgeting strategy.
Wayne bring cost performance report postings up to date on the
Engineering web.
- Discussion and current
assessment of proposed new work currently not in the budget (or
under-budgeted).
- Third coil winding
fixture. Likely to be needed in a few months to recover or
accelerate coil winding schedule. Immediate actions (Larry to follow
up): determine whether any design changes are needed, or can we
just duplicate the existing design? What are the long-lead items?
Can the parts be procured instead of built in house? Hutch and
Ron to identify source term for funds (e.g., end-of-year procurement
accruals).
- Additional cold
testing beyond C1: decide after detailed review of C1 test
results. Next window is expected to be ~January, 2007 when NSTX starts
its FY-07 run. Well before the next Lehman review (nominally November)
we need to decide what we’re doing. Those in attendance did not
immediately see a compelling case for additional cold testing, given the
project’s tight budget.
- Flux loops on the MC
shell: Would likely be installed on the inside surface of the MC
shell near the peaks of low-order eigenmodes. These tend to be in the wing
region. They might span multiple shell sectors, in which case they
would logically be installed on 3-coil subassemblies. While there is a
programmatic benefit (constraining the more important eddy current
eigenmodes in magnetic loops data analysis), there are cost risks to the MIE
project. The vacuum vessel flux loops have cost much more than originally
budgeted, and continue to run large variances. There is impact on other work
packages (WBS 14, 18, 82). It is assumed that the MC flux loops would
have similar engineering requirements. Does the programmatic benefit
justify accepting the cost risk given the project’s tight finances?
Decide soon (after Mike Z returns from travel).
- Trim coils on the MC
shell: the MC shell is potentially an attractive place to mount
trim coils to compensate field errors with m > 2 or 3. They would
have to be installed during FPA, probably before the TF coils go on. They
cannot be retro-fit after the machine is built. However, there is no
budget for them. Recent incremental budget proposals for research prep
have not identified this as a priority, so it may be a non-issue. (Mike
Z. to comment)
- Magnetic
alignment: Method proposed by Mike Z. has been documented in an
EPS paper. The benefit is that it can reduce the risk of uncorrectable field
errors in the finished machine due to assembly errors caused by uncertain
knowledge of the current center location. The risk is the uncertain
cost and schedule impacts on the project due to the developmental nature of
the method. There is no time or budget for an R&D program that
appears to be needed to develop the technique. Decide soon (after Mike
Z returns from travel).
3.
Risks
- C1 cold testing schedule.
Testing went well last week, but the temperature difference between the MCWF
and winding pack was larger than desired. This may complicate comparison of
test data to analysis predictions. Will likely try to further cool the winding
form and continue cold testing this week, assuming NSTX returns to operation.
A meeting to review program status is scheduled for Tuesday June 20.
- C2 meggar re-test.
What voltage? It was recommended that we adhere to the required
manufacturing test voltage of 7.5 kV for C2. Larry follow up
with winding team. Wayne follow-up with dissenters, if any.
- Magnetic loops (WBS 3) cost
control issues. Variances are growing despite management direction to limit
costs. Wayne follow up with Labik.
- Are we accomplishing what
we planned to on FPA? Larry says yes: metrology, operation of
fixture, flux loop installation trials. Why did the fixture mounting
plate holes not align with the Port 12 flange holes? Larry follow
up and let everyone know.
- MC shear plate tests: are
they on schedule to support design needs? Mike C. follow up.
- Completion of VV design.
Boot fit-up at the MC shell joints is the main outstanding issue,
requiring additional design work. FDR chits still have to be closed out.
When will the Title II work be complete? Mike C. follow up.
- MC winding schedule:
good progress recently in efforts to hire four new technicians.
Good applicants are being interviewed, offers are expected to go out
soon. Allowing for July 4 holiday and training requirements, expect new
staff to be fully on board about mid-July.
(Larry)
4. Next SIT Meeting:
t.b.a.
Summary by:
Hutch
Neilson