From: Hutch Neilson
Sent: Wednesday, June 21, 2006 5:53 
PM
To: Hutch Neilson; Gregory Pitonak; Jeffrey Makiel; Barry Sullivan; 
Ronald L. Strykowsky; Jim Lyon
Cc: James H. Chrzanowski; Michael E. 
Viola; Pamela Hampton; Phil Heitzenroeder; Wayne T. Reiersen; Richard J. 
Hawryluk; Sam Barish; Robert J. Goldston; Gene Nardella; Bradley E. Nelson; 
Michael R. Kalish
Subject: 20060621 NCSX weekly update
There will be no telecon this week. 
 Call or e-mail if there are any questions.  Hutch
NCSX 
Weekly Update of 06/21/06
1. Modular Coil fabrication 
(PPPL)
MC Fabrication summary status:
4 in 
  production
2 completed through VPI and being 
tested
C-1 Coil
  - Planned cold testing 
  program was successfully carried out last week. Good data were obtained but 
  analysis will take some time. 
  
- Some additional shots will 
  be taken this week to extend the data base to higher temperatures. 
  
 
C-2 Coil
  - Passed meggar test at 7.5 
  kV. 
 
C-3 Coil
  - VPI Prep completed and 
  moved to autoclave June 21. Milestone was June 
9.
 
C-4 Coil
  - Both sides have been wound. 
  Winding pack metrology and dimensional adjustments have been completed. 
     
  
- VPI prep completion 
  milestone is July 20. On schedule.
 
C-5 Coil
  - Cladding installation in 
  progress.  Will move to winding station June 22. 
  
- VPI prep completion 
  milestone is August 16. Currently 13 days behind 
  schedule.
 
A-1 Coil
  - Moved to manufacturing 
  facility.  Preparing to install in winding ring and prep station later 
  this week. 
  
- VPI prep completion 
  milestone is October 2. Currently 11 days behind 
  schedule.
 
2. MCWF procurement (Energy Industries of 
Ohio)
MCWF summary status:
All 18 castings 
  have been poured
2 in foundry operations
10 in machining operations
6 
  delivered.
Machining operations (Major Tool and 
Machine):
A-2
  - 5-axis operations 
  proceeding very well and nearly completed. 
  
- The project’s delivery 
  milestone is July 13, but MTM is projecting shipment around the end of 
  June.
 
A-3 and A-4
  - The A-3 is making good 
  progress in 3-axis operations on the Mitsu-40. Forecast to move to U5 around 
  July 5. 
  
- The A-4 has completed some 
  3-axis operations on the Mitsu-30 and is in the queue for the Mitsu-40. 
  
  
- The project’s delivery 
  milestones are August 16 and October 24. 
 
B-1 and 
B-2
  - The B-1 and B-2 are 
  alternating in roughing operations on the Lucas 40T, and some on the Mitsu-30. 
  
  
- The project’s delivery 
  milestones are September 20 and November 29.
 
A-5, A-6, B3, B4, and 
C-6
  - The A-5, A-6, B-3, B-4, and 
  C-6 are in the queue for machining.
 
Foundry operations (MetalTek 
International): 
B-5 and B-6
  - The B-5 is passed final 
  X-ray at MQS and returned to MetalTek for final processing. 
  
- The B-6 is undergoing weld 
  upgrades. 
  
- Both B-5 and B-6 are 
  expected to ship to MTM in a single shipment at the end of 
  June.
 
3. VVSA procurement (Major Tool and 
Machine)
  - VVSA #2 is having its ports 
  aligned and prepped. Currently finishing the Port 4’s and the 
  domes.
 
  - VVSA #3: Ports and end 
  flanges are being installed. Some re-work at the end flanges will be 
  performed, similar to VVSA#1.
 
4. TF Assemblies procurement (Everson Tesla, 
Incorporated)
  - Fermi Lab is preparing to 
  ship the induction braze unit to ETI.
 
  - Mold and winding fixture 
  designs have been developed. Fabrication plans are being discussed with 
  outside machine shop.
 
  - Sample bend tests have made 
  good progress. Tooling adjustments are being made based on results to 
  date.
 
  - Tesla personnel are meeting 
  with stainless steel suppliers for the wedge pieces. Material delivery 
  schedule is an issue. There is potentially a 3 week slip in the schedule, 
  which ETI is working to resolve.
 
  - Mike Kalish and other PPPL 
  staff have made weekly visits to ETI. Recent topics have been inspection 
  requirements and location of braze joints.
 
Hutch 
Neilson