From: Hutch Neilson [hneilson@pppl.gov]
Sent: Tuesday,
March 14, 2006 8:22 AM
To: Bradley E. Nelson; Hutch Neilson; Jim Lyon;
Lawrence E. Dudek; Mike Williams; Michael C. Zarnstorff; Phil Heitzenroeder;
Wayne T. Reiersen; Ronald L. Strykowsky
Subject: Summary of NCSX SIT
Meeting of 3/13/06
Summary
of NCSX System Integration Team (SIT) Meeting of Monday, March 13,
2006
1. Management items
- February Cost Performance
Report summary. (Ron)
- Cost variances continue
to increase, but schedule variances are stable.
- VVSA, TF, and Mod Coil
final design dominate the schedule variances.
- Mod coil winding &
testing, project management & integration, VV, TF, and power systems are
cost variance drivers.
- VV design is running up
cost and schedule variances because deliverables are not being completed.
FDR of heating/cooling tubes and hold-down clamps is planned to occur
in the next few weeks. This is a key step in bringing the work to closure.
More below.
- Lehman Review
preparation
- May Lehman review will be
used by DOE to assess whether project can be completed within the approved
baseline.
- ETC update will be done
in preparation for the Lehman review. Incorporate last 6 months of
experience and planning into estimates. Identify offsetting work reductions
in future work. Scrutinize plans for new work. Update risk assessment and
mitigation plans.
- ETC call was issued by
Ron last Friday. Input due 3/24. Management reviews will
follow.
2. Risks
- Completing VV design
deliverables (Brad)
- FDR of heating/cooling
tubes and clamps planned for this week.
- The heating/cooling tube
hold-down clamps will be prototyped to be sure they can be economically
installed while matching the contours of the vacuum vessel. Design changes
could result, depending upon the outcome. It was agreed that this should be
done, due to the large number of clamps and the cost and schedule risks if
manufacturability is a problem. Brad send drawings to Larry. Larry will
lead the prototyping.
- VV drawings need to be
issued: flexible tube specification drawings, saddles and clips, routing of
the tubes(?), Port 12 heater tape arrangement (one or two?)
- An integrated test of the
port temperature control, boot design, and pourable insulation has been
proposed as part of closing out the vacuum vessel design. This is
currently unbudgeted. The cost and schedule need to be estimated so they can
be weighed against the benefits. What are the risks if we don’t do it?
Brad to include this proposal in ETC update so we can decide
one way or the other.
- Modular coil inter-coil
shear handling (Brad)
- Recent global analyses by
Brooks and Fan have highlighted an issue: normal force on the modular coil
joints is insufficient to provide enough friction to react the shear forces.
Independent checks are in progress and there is some possibility it
will prove to be a non-issue, but Brad states that we should assume it is an
issue. Wayne has added it to the critical issues list.
- One possible solution is
to incorporate a key feature into the design of the intercoil shims.
Epoxy fillers could be used to avoid the need for precision machining.
Other possibilities were described.
- The current plan is to
address this issue as part of the coil interface hardware design task (Job
1421) scheduled to start later this FY, after MC final design is completed.
Brad and Ron: Check schedule to
confirm.
- Modular coil fabrication
(Larry)
- Type A cladding drawings
have not been delivered. Risk that we will not have needed parts in time, or
may have to use costly in-house fabrication.
Brad
- VVSA Schedule &
Dimensional Conformance
- In-process VVSA
dimensional data provided by supplier has raised concerns that the finished
VVSA #1 will not conform to spec. Data are preliminary and incomplete
so it is difficult to know how (or whether) to react to it.
- More measurements will
delay schedule but may be necessary.
- Follow-up meetings are
planned. Brad and Phil
- Title III design on VVSA
and MCWF.
- Sense is that costs have
greatly exceeded expectations, although Title III costs are not captured
separately.
- One step is to be sure we
minimize the number of attendees at meetings called to respond to supplier
issues.
- It was also suggested
that the project should take a firmer stand in responding to supplier
requests for deviations or acceptance of non-conformances. Hutch
follow up with Phil
- MC fabrication cost
control. (Mike W., Larry)
- Data are reviewed in
separate weekly meetings. Evidence of learning curve improvements are seen,
but more time is needed to establish firm
trends.
4. Next SIT Meeting: March 27 at
11:00.
Summary by:
Hutch Neilson