From: Hutch Neilson
Sent: Monday, May 22, 2006 5:48
PM
To: Mike Williams; Lawrence E. Dudek; Ronald L. Strykowsky; Wayne
T. Reiersen; James H. Chrzanowski
Subject: Re: Meeting on MC winding
cost & schedule, Monday May 22 at 2:30
Folks,
My conclusions of today’s meeting are as
follows. Please correct or supplement as
appropriate.
- The highest priority at
this time is to get two more technicians (affirming a previous decision).
This is needed to get from zero to one shift per day on Station 1b, in
practice, and maintain production through the summer vacation season.
All agree that we are staff-limited.
- After that, the next
highest priority is probably to get still more staff assigned to NCSX coil
winding, enough so we can get to two shifts per day on Station 1b, as needed.
- A holding fixture ($15k)
would allow us to process 4 ring-mounted coils simultaneously, shaving one
month off the schedule, but still missing the desired November, 2007
completion date by a month. Moreover, the equivalent benefit could be realized
by instead laying the coil down between VPI and post-VPI operations. The cost
is removing the weights in order to attach the lifting bar to the ring, then
re-installing the weights when we are reading to resume processing. The cost
over the remaining coils might be about the same as buying a holding fixture,
except spent on a pay-as-you-go basis.
- Wayne’s analysis shows that
in order to meet the Nov., 2007 completion date, a full 3rd winding
station ($70K) will be required. It will also likely be required if we
need to speed up at the end to recover schedule, or to take advantage if EIO
is able to speed up MCWF deliveries. The risk is that we buy the 3rd
station, but then don’t realize the financial benefit from it, either because
the MCWFs don’t keep up, or because our efficiency goes down when we go from
two to three winding stations.
- I expect that by October or
November of this year we will want the third winding station. At this time, we
have not identified a source of FY-06 funds to pay for it, but we should
pursue that (Hutch, Ron). In the meantime, we should not build
any less capable fixturing that isn’t on a path to a full winding
station.
Hutch
on 5/17/06 2:30 PM, Hutch Neilson
wrote:
Weekly meeting on
MC winding cost and schedule, Monday, May 22 at 2:30 (special time), in
my office.
- Shall we install an
additional fixture? (Wayne)
- Ongoing topics (Larry)
Report updates and any issues needing
attention.
- Cost trends
- Schedule performance:
Completion of coils through VPI prep.
- Process improvement
- Crew management issues
(overtime, productivity, organization, shift work, charts, training,
etc.)
Hutch