From: Hutch Neilson
Sent: Monday, April 09, 2007 9:48
PM
To: Bradley E. Nelson; Hutch Neilson; Jim Lyon; Lawrence E. Dudek;
Mike Williams; Michael C. Zarnstorff; Phil Heitzenroeder; Wayne T. Reiersen;
Ronald L. Strykowsky; Mike Cole
Subject: Summary of NCSX SIT Meeting
of 04/09/07
Summary of NCSX
System Integration Team (SIT) Meeting of Monday, April 9, 2007
1.
Readiness start MC assembly in May: Schedule Risks
- We reviewed the schedule
risks for starting MC assembly. The schedule issued at last week’s SIT
forecast that we would start at the end of July. This would meet our
Level II milestone if achieved, but has zero schedule float so risk of failure
is high. Moreover it does not satisfy our management goal to start in
May, which is important for underpinning our new ETC (due in June) and
demonstrating convincing progress at the July Lehman review. We need to
take measures to recover this schedule slippage, by working on the two main
critical path activities
- Modular coil prep
- Inboard
shim
- Modular coil prep
Larry
- Drawings for the
additional flange holes have been issued. The C2 coil has been taken to the
RESA building for machining and grinding operations to start.
- Overtime is an option for
managing schedule risks, but will proceed deliberately at first to be sure
process is worked out.
- Inboard shim.
Wayne
- Stresses in the fillet
weld (shear puck design) have been analyzed. Need to check applied
loads and allowables. Mike C.
- Weld test will be
performed to check distortion and determine how good a fit-up can be
obtained around the shear puck. Parts for the test have been
fabricated and the test will be carried out this week. A significant risk is
seen that the weld distortion will be too large to obtain satisfactory
fit-up. Larry.
- New alumina friction
tests will be performed with the mating steel surface finish more
representative of the actual modular coil flanges. (Friction shim design)
Earlier tests may have had too smooth a finish. Gettelfinger.
- It was observed that the
shear puck design has high schedule risks because of the need for
development trials, the risk that those trials will have unsatisfactory
outcomes or require multiple iterations, and demanding assembly
requirements. The friction shim design (“Plan B” introduced by Wayne
over the weekend) appears to offer reduced schedule risks and therefore may
be more attractive. Fit-up issue should be resolved via A-A fit-up
trials.
- We need to converge this
week on a design that has acceptable schedule risks.
Hutch
- A-A fitup trials
Larry
- After some delays, trials
should proceed tomorrow. Crane operators are booked.
- This test expected to
confirm that constant-thickness shims are acceptable, and establish the
range and gradation of shim
thicknesses.
2. ETC Update Issues
- Status summary was issued
by Ron. A few more reviews were conducted last week, including WBS 18
and 7. Estimates for about 2/3 of the work have been submitted as of
last week, and are in various stages of review.
- Additional submissions and
reviews are planned for this week. Ron
3. New FY09-11 budget guidance from
DOE
- We will focus primarily on
FY-09 for our initial response due April 18. Beyond that depends on the
outcome of our ETC activity.
Summary by:
Hutch
Neilson