The following list represents prototyping efforts needed.
In all cases the number represents weeks for 2.5 men (=5 man weeks) and the status
 
STATION 1
diagnostic loop templates     3    complete
cooling tube layout              2    complete
diagnostic loop installation   1    complete
cooling tube clamps            3    60%
cooling tube risers              1    20%
 
STATION 2
Coil interferences  C-C       1    100%
Coil interferences  C-B        1    50%
Coil interferences  B-A        1  
Coil interferences  A-A        1  
Flange Alignment                3    60%
Bolt torqueing                       2    20%
fiducial types                      1
fiducial locations                 1
Bolt shim "grinding"             1
Shear strength (coating?)    2    Geoff (~50%)
nose shim                           2
bushing                              2
epoxy squirt                        3
40 degree stand                  1
 
STATION 3
vessel fixturing adjustments  1
new actuators                     1
vertical flange joint              2
lower supports                    1
 
STATION 4
fiducial locations                 1
port extension support         1
port extension alignment      1
 
STATION 5
fixturing adjustments           1
fiducial locations                1
clamp adjustments              1
 