From: Steve Raftopoulos
Sent: Tuesday, June 14, 2005 
12:02 PM
To: David E. Williamson; nelsonbe@ornl.gov; Wayne T. 
Reiersen; ldudek; Hutch Neilson; Michael C. Zarnstorff; Brentley C. Stratton; 
Phil Heitzenroeder
Cc: Thomas G. Meighan; James H. Chrzanowski; 
fterlitz; ekearns; manderson; chause; egilsenan
Subject: Coil Winding 
Activities Update
Folks,
Here's a status on where we 
are.
TRC: 
  - The coil is being prepared for the final clamps.  The G11 pads are 
  all cleaned up and we are in the process of digging out the RTV from the bolt 
  holes 
  
- The coils clamps are due to ship today, while the silver plated screws 
  should have shipped already. 
  
- Successful hydrostatic test of the cooling tube was performed this 
  morning.  We will perform a flow test after lunch. 
  
- We detected a short between the cooling line(s) and the casting.  The 
  shorts are occurring in the upper chill plate which is staked to the vertical 
  cladding.  We suspect that the staking process damages the insulation 
  (Kapton sheet on the back of the cladding)  and some part of the VPI (or 
  post VPI) process compromised it the rest of the way. The resistance is ~0.5 
  ohms.  This short wasn't there before VPI. 
Facility 
Prep: 
  - Work continues on stations 1Aand 4.  We are in the process of 
  anchoring down the Mod Coil-to-Ring assembly fixture 
  
- We "found" a good sized gantry/A-frame hoist which we hope to use on 
  station 1A.  We will try it out this afternoon. 
Winding 
Pack stabilization trials: 
  - The Straight tee is stripped. 
  
- We have machined conical seats into the end caps for Romer alignment(s). 
  
- We are stud-welding treaded rod onto the tee for the lower leg of the side 
  clamp. 
  
- B. Stratton, Mike Z. and I met yesterday and agreed upon a set binding 
  configurations that we will try.
  
Steve Raftopoulos
Senior Staff 
Engineer
Princeton Plasma Physics Laboratory
P.O. Box 451, Princeton, NJ 
08543
(609) 243-3626 Voice
(609) 243-3248 Fax