From: David Johnson [djohnson@pppl.gov]
Sent: Wednesday, January 28, 2004 1:40 PM
To: Bob Simmons
Subject: Re: ECP-04-004 (PDR to CD-2 Baseline) Ready for Review and Comment
Bob,

I have reviewed the revisions in the CD-2 Cost and Schedule Baseline documents and I have no comments.  Looks ok to me...

Dave

Folks,
 
As a last step in going from the PDR baseline to the CD-2 baseline, we need to approve an ECP that documents the process and provides an audit trail.  ECP-04-004, which many of you contributed to, does that. 
 
We plan on holding a CCB on this ECP on Wednesday, Feb 11th, at 3:00 pm, immediately following the WBS 1 Engineering Meeting.  Please provide any comments you have by Monday, Feb 9th, to me so that I can present them at the CCB meeting.
 
The ECP can be found at the following NCSX Engineering Web page: < http://ncsx.pppl.gov/SystemsEngineering/Config_Mgmt/FY2004_ECPs/FY2004_ECPs_index.htm >.  I have attached a sample ECP Page II for your use. However, if you have no comments, or only minor editorial comments, a simple e-mail will suffice.
 
This ECP includes the Cover Page and Page I and then 4 attachments:
(1)     Revised Funding Profile and Budget Totals
(2)     Revised DOE Project Milestones Table
(3)     Detailed Breakdown of Cost Impacts
(4)     Primavera Database showing revised project schedule and cost baselines
 
If you have any questions, please contact me.
 
Thanks,
 
Bob S.
 
Bob Simmons
NCSX Systems Engineering Support Manager
Princeton Plasma Physics Laboratory (PPPL)
Tel #: (609) 243-2766
Fax #: (609) 243-3030
 

Content-Type: application/msword;
       name="ECP_PART_II.doc"
Content-Description: ECP_PART_II.doc
Content-Disposition: attachment;
      filename="ECP_PART_II.doc"
Attachment converted: Macintosh HD:ECP_PART_II.doc (WDBN/MSWD) (000DF1C0)