Bob,
I have reviewed the revisions in the CD-2 Cost and Schedule Baseline
documents and I have no comments. Looks ok to me...
Dave
Folks,
As a last step in
going from the PDR baseline to the CD-2 baseline, we need to approve an ECP
that documents the process and provides an audit trail. ECP-04-004,
which many of you contributed to, does that.
We plan on holding a
CCB on this ECP on Wednesday, Feb 11th, at 3:00 pm, immediately following the
WBS 1 Engineering Meeting. Please provide any comments you have by
Monday, Feb 9th, to me so that I can present them at the CCB
meeting.
The ECP can be found
at the following NCSX Engineering Web page: < http://ncsx.pppl.gov/SystemsEngineering/Config_Mgmt/FY2004_ECPs/FY2004_ECPs_index.htm >. I have attached a sample ECP Page II for your
use. However, if you have no comments, or only minor editorial comments, a
simple e-mail will suffice.
This ECP includes the
Cover Page and Page I and then 4 attachments:
(1) Revised
Funding Profile and Budget Totals
(2) Revised DOE
Project Milestones Table
(3) Detailed
Breakdown of Cost Impacts
(4) Primavera
Database showing revised project schedule and cost baselines
If you have any
questions, please contact me.
Thanks,
Bob
S.
Bob
Simmons
NCSX Systems
Engineering Support Manager
Princeton Plasma
Physics Laboratory (PPPL)
Tel #: (609)
243-2766
Fax #: (609)
243-3030
Content-Type:
application/msword;
name="ECP_PART_II.doc"
Content-Description:
ECP_PART_II.doc
Content-Disposition:
attachment;
filename="ECP_PART_II.doc"
Attachment converted: Macintosh
HD:ECP_PART_II.doc (WDBN/MSWD) (000DF1C0)