From: Hutch Neilson [hneilson@pppl.gov]
Sent: Friday, May 14, 2004 2:10 PM
To: Bob Simmons
Cc: Brad Nelson; Wayne T. Reiersen; Paul Goranson; Michael Zarnstorff
Subject: Re: Resolution of Comments on ECP-04-008
Our design has always had ports that extend all the way through the cryostat, that is not new.  I do not see any reason to change that just because we are putting in a flange and transitioning to stainless.  For good integration the  design needs  to have ports coming all the way out through the cryostat, to claim space inside and on the surface of the cryostat and to provide a way for diagnostics to interface. There is no money in the budget to design a large number of custom extensions. In those cases (relatively few I expect) where somebody wants to modify the geometry of a removable extension, it will be entertained as a change proposal and accommodated as far as possible.

I thought this is what was decided.  We are probably not including the removable extensions in the VVSA contract, but they should be included somewhere in WBS 12.

If I’m off base I’m sure someone will let me know,

Hutch



On 5/14/04 13:07, "Bob Simmons"  wrote:

Hi Hutch,
 
All your comments have been incorporated with the exception of the following items:
 
(1)
   Port Extensions: The outer port extensions are NOT included in this estimate.  Mike Z. has opined that we should just go ahead now and procure generic extensions thru the cryostat.  Brad is of the opinion that there is no real need to do that now.  It will probably be several years before diagnostics comes up with specific requirements, so any generic port extension runs the risk of not being adequate.  We can do either approach – just let me know so that I can get Brad to estimate cost of the 33 generic port extensions.
(2)
   Evaluation of Options:  I really messed this one up.  Port configuration studies considered fewer and more ports (up to 45 new ports).  Fewer rejected since did not provide sufficient diagnostic flexibility.  45 ports were a non-starter also since the 6 new ports each at port 13 and port 14 just did not leave sufficient metal for structural support.  The 33 new ports provided the maximum flexibility.
 
Draft B attached for your review and comment.  Still missing affirmative statement of impacts on other WBS elements (although it appears that there is no impact on WBS 14).
 
Bob S.
 
Bob Simmons
NCSX Systems Engineering Support Manager
Princeton Plasma Physics Laboratory (PPPL)
Tel #: (609) 243-2766
Fax #: (609) 243-3030