Folks
My only comment on the cost breakdown is to add some time and $ for shipping and increase the management cost to $35k (average of high and low management costs). I have attached my version of the schedule, since I could not hear the conversation very well. If the losing contractor only goes through step 2, we only double-spend $75k, counting management costs. If we pick a winner by August 12, maybe we would limit the double expenditure to $25 k.
Brad
-----Original
Message-----
From: Wayne
Reiersen [mailto:reiersen@pppl.gov]
Sent: Thursday, June 17, 2004 3:56
PM
To: Bob Simmons
Cc: Phil Heitzenroeder; Hutch Neilson;
Nelson, Brad E.
Subject:
Incremental MCWF costs
Bob,
Phil’s table is shown below. The incremental cost of having the second supplier begin work on a prototype reflecting the production coil design should be the cost of the first two tasks ($50K) plus order 15% per Phil’s guidance. I would round it off to $60K. Comments?
Wayne