List of Items for Future ECPs |
||
|
|
Item | Responsibility |
|
|
Vacuum Vessel Spacer Piece Installation Fixture (WBS 17) - Gettlefinger |
Gettlefinger |
| WBS12/WBS 4 ICD CableRouting from Panel to Heaters | Goranson | |
| WBS 1/WBS 4 Interfaces - need to Add Cost of Leads from Power Panels to Equipment | WBS 13/14/15/16/17 Managers | |
| VVSA S/C - Marking of Stud Locations & Oversight & Support | Viola/Strykowsky | |
| MC Winding Final Design | Williamson/Strykowsky | |
| TRC Close-Out Costs | Chrzanowski/Strykowsky | |
| MCWF Fracture Analysis | Williamson/Strykowsky | |
| Metrology Support Program | Raftopoulos/Strykowsky | |
| FP Assy Facility Prep Dsn & Install | Brown/Strykowsky | |
|