RFD Number |
Associated ECP Number |
Title |
Date Approved or
Disapproved |
RFD Status |
|
|
|
|
|
WBS 14 Requests for
Deviation |
|
|
14-029 |
|
Change of Load &
Flat Washer Material |
10/22/2007 |
Approved.
Note placed on
drawings. |
14-028 |
|
Minimum Wall
Thickness for Nut Clearance on Type C Modular Coils |
5/15/2007 |
Approved.
Note placed on
drawing. |
14-027 |
|
Radiographic Waiver For Weld Upgrade To C6 |
3/12/2007 |
Approved. |
14-026 |
|
Remaining B Castings (B2 thru B6) Thin Wall
Condition |
11/20/2006 |
Approved. |
14-025 |
|
B Castings
Counterbore Options |
10/5/2006 |
Approved.
Note placed on
drawing. |
14-024 |
|
Bearing Plate Modification for
Remaining B Castings |
10/5/2006 |
Approved.
Note placed on
drawing. |
14-023R1 |
|
Vacuum Vessel Support Boss |
10/5/2006 |
Approved.
Note placed on
drawing. |
14-022 |
|
Reorientation of Type
B MCWFs Lead Slots |
5/24/2006 |
Approved.
Note placed on
drawing. |
14-021 |
|
Substitution of
Chiller Plate Material |
5/16/2006 |
Approved.
Note placed on
drawing. |
14-020 |
|
Type A1
MCWF Flange Hole Modifications |
5/22/2006 |
Approved.
ECN 5128 will
incorporate this change. |
14-019 |
|
Adding
Lifting Holes in Poloidal Break Shims |
4/13/2006 |
Approved.
ECN 5112 added as note. |
14-018R2 |
|
Type A2-A6
MCWF Flange Hole Modifications |
5/24/2006 |
Approved.
ECN 5128R1 will
incorporate this change. |
14-017 |
|
Thermocouple Hole
Location/Shape Changes |
4/3/2006 |
Approved. |
14-016 |
|
Bearing Plate
Material Change |
3/31/2006 |
Approved.
ECN 5059R3 added as
note. |
14-015 |
042 |
MCWF Type C Port
Openings |
3/21/2006 |
Approved. |
14-014 |
|
Machine Port Openings
at Common Angle |
2/21/2006 |
Approved. |
14-013R1 |
042 |
Change to Type C-4 Through C-6
Flange Seats from a Spherical Seat to a Conical Seat |
2/17/2006 |
Approved. |
14-012 |
042 |
Relaxation of
Tolerances on Remaining Type C Castings |
1/17/2006 |
Approved. |
14-011 |
|
Change in Magnetic
Permeability for MCWF Bearing Plates |
12/20/2005 |
Approved. |
14-010 |
|
Material Change for
Terminal Lugs for MCWF |
12/14/2005 |
Approved. Add
note to impacted drawing noting material change to C11000, ¼ hard. |
14-009R1 |
038 |
Proposed Drawing
Changes Resulting from Inspection of C1 Casting at PPPL |
10/24/2005 |
Approved. CSPEC and
Drawings to be updated by Oct 31st. |
14-008 |
038 |
For C1 Only. Add
Additional G11CR Shim Pieces for the Poloidal Break |
9/22/2005 |
Approved. CSPEC and
Drawings will
be updated by Oct 31st. |
14-007 |
|
Modular Coil Jumper
Material Substitution |
9/30/2005 |
Approved. CSPEC and
Drawings will
be updated by Oct 31st. |
14-006 |
038 |
Deletion of Erroneous
Requirement in Section 3.1.1.6.1 of the Modular Coil CSPEC
(NCSX-CSPEC-141-03) |
9/15/2005 |
Approved. CSPEC will
be updated by Oct 31st. |
14-005 |
|
For C1 only -Waiver
of Post Machining Inspection for Internal Defects in High Stress
Area & Radiography on Weld Repair |
9/15/2005 |
Approved. |
14-004 |
N/A |
Add fillets to
Modular Coil Lower Lead Blocks to Aid Machining |
7/25/2005 |
Approved with caveat
that mating parts be chamfered to clear added fillets. |
14-003 |
033 |
Relaxation of
Material Testing Requirements |
6/8/2005 |
Authorizes deviation
to not require testing in transverse and longitudinal directions. |
14-002 |
N/A |
Change in Dimensional
Inspection Requirements for the C1 Casting |
4/15/2005 |
Deleted requirement for second dimensional inspection => deemed
redundant. |
14-001 |
028 |
RFD-14-001, Revised
Location of Part Number in MCWF Casting |
3/30/2005 |
Drawing
SE-141-114 shows the reference location of the pattern/casting
identification number for Type A coils. No change in that drawing is
planned, at least not until all of the Type A coils are fabricated. |